INSTALLATIEHANDLEIDING – P12
VERSION 0129NM02INT01
INSTRUCTION MANUAL – P12 |
P12
06A0RNM20ENG05
Wiring advice*
Power cable size
Earthing advice*
Required nominal
input voltage @
charge point
MCB
RCD
Load Shedding
module (7,4kW)
Load Shedding
module (11kW)
5 wires Ø 1,5mm
2
accessories cable
for EV- and ZE-Ready
installation
Ø 10mm - Ø 22,5mm
10mm
2
solid wire
6mm
2
stranded wire with end ferrules
PE-cable (Pen conductor is not allowed)
Separately installed grounding electrode < 100
Ohm spreading resistance
230V+N +/-10% 50Hz
400V (3 x 230V+N) +/-10% 50Hz
Cable grommets sizes
Maximum cable terminal block
TN-system
TT-system
Single phase**
Triple phase**
4. INSTALLATION DETAILS
The electrician is responsible for selecting a cable thickness & safety components appropriate
for the specific situation and according to regulations;
* The electrician is always responsible for selecting a cable thickness appropriate for the specific situation and
according to regulations;
** 3-phase charge point can also be connected to 1-phase. In this case the charge point can only charge on
1-phase;
*** The electrician must select a suitable MCB with C-characteristic to match the amperage setting of the charge
point, taking into account MCB manufacturer specifications and EV-Ready guidelines;
NOTE:
The charge point can be set between 16A / 20A / 25A and 32A (depending on version), see chapter 6.
- Wire for the maximum hardware amperage under continuous load;
- Calculate with a COS-Phi of 0.8;
- Calculate with a max allowable voltage drop over the cable of 2%;
- Use shielded cable for underground wiring
C-characteristic***
30mA Type B, or 30mA Type A (Hi, Hpi, Si) in combination with appropriate
equipment that guarantees power shutdown at DC leakage of more than 6mA
Standard cable of 2x 1,5mm
2
With a maximum length of 100 meter
Standard CAT5 or CAT6 Ethernet cable (UTP cable with RJ12 6P6C straight
connectors). With a maximum length of 100 meter
- L1, L2, L3, N + PE;
L1 & N for connecting the shunt
L2 & L3 for connecting the ON/OFF Peak signal
- Always connect PE to terminal blocks of charge point and at distribution board
- Use shielded cable for underground wiring