Generalsafetyregulations
SA3-SInstallation&CommissioningManual
3
Risk of material damage
The following shall always apply during all work on the installation:
Electrostatic charging
›Keep the electronic assembly in its original packaging until installation.
›Before opening the original packaging, a static discharge must be performed. To do this, touch a grounded
piece of metal.
›During work on electronic assemblies, periodically perform this discharge procedure.
Electronic assemblies are destroyed by defective, interchanged or incorrectly mounted connectors, short-circui-
ting or excess voltage.
›Check plugs for mechanical damage.
›Never change pre-assembled connectors or cables.
›Only connect loose or torn off wires according to circuit diagram details if this is possible on site (suitable mate-
rial and tools must be available).
›Pay attention to coding pins and latch lugs.
2.3
Safetyregulations
General
›The instructions of the lift manufacturer and the instructions in this manual must be followed during installation
and commissioning of the safety device.
›The shaft must be secured against unauthorised trespassing during installation, commissioning, inspection and
maintenance.
›Assemblies, devices and cables must be installed and fastened securely and permanently.
›Loads must be moved with suitable aids (lift trucks, hoisting gear etc.).
›Sharp and pointed tools or other potentially dangerous objects may only be carried along in clothing if suitable
protective measures have been taken to rule out any danger.
›Alcohol and drugs must not be consumed before and during installation and commissioning.
Documentation
›A copy of the installation and commissioning manual must be available to the installing engineer at the time of
installing and commissioning.
›A copy of the installation and commissioning manual and the wiring diagrams must be kept in the control cabi-
net at all times after installation.
›The wiring diagrams supplied with the SA3-S safety device are binding. Changes must only be made after con-
sulting NEW
LIFT
and must be documented in writing on the system.
›The factory-side inspection records of the SA3-S safety device remain with the manufacturer.
Electricity
›Regulations for installing and operating electrical equipment (VDE 0100) and regulations of local utilities must
be followed.
›The specified distances between different electrical assemblies must be controlled and maintained.
›All installation work must be carried out with the system shut down and off circuit.
›All cables and wires must be installed with sufficient strain relief.
›The neutral and ground wires must be routed separately.