2. When the L900 MIU is installed correctly, its ID number(s)
and meter reading(s) appear on the display of the HHU. Verify
the correct meter reading(s) by comparing it to the meter’s dial.
If the reading(s) is the same, proceed to the next section.
3. If a meter reading does not appear on the HHU display, or the
meter reading in the HHU display is not the same as the
reading on the meter’s dial:
l
Magnet swipe the L900 MIU using the magnet.
l
Verify all electrical connections.
l
Test the installation again.
4. If a ProRead encoder register is used:
l
Ensure the unit is programmed in three-wire mode.
l
Verify all electrical connections.
l
Magnet swipe the L900 MIU. (See Step 1.)
If a problem still exists, contact your Neptune Sales
Representative.
Completing the Installation
To complete the installation, follow these steps.
Figure 22 – Install Seal Wire
1. To complete the installation, install a seal wire or seal
clip through the seal holes at the bottom of the main
housing. See Figure 22.
2. Verify that the requirements of the site work order have
been met and that you have recorded all information.
3. Clean up the installation site before leaving.
L900 MIU Pit and Wall Installation and Maintenance Guide
21
Chapter 4: Wall Installation
Summary of Contents for L900 MIU Pit
Page 2: ......
Page 3: ...L900 MIU Pit and Wall Installation and Maintenance Guide...