1. Turning on the Server
Express5800/T110g-E User’s Guide
117
Chapter 3 Setup
1.
Turning on the Server
Turn on the server by using the following procedure.
Important
Wait for at least 30 seconds before turning on the server again after the
power has been turned off.
When the optional RAID controller N8103-167 is installed, wait for at least
90 seconds before turning on the server.
1. Disconnect Flash FDD if applicable.
2. Turn on the peripheral devices such as display unit.
Note
If the power cord is connected to power control system such as an Uninterruptible
Power Supply (UPS), make sure that the power control system is turned on.
3. If POWER LED lights amber, wait until POWER LED is unlit.
4. Press POWER Switch at the front of the server.
POWER LED is turned on green and after a while, NEC
logo appears on the display.
While the logo is being displayed, the self-diagnostic
program (POST) runs and diagnoses the hardware. For
details, see
.
POWER
LED
POWER
switch