Step 3: Constructing the liquid drain trench
Place the plain end of the 19mm
Liquid Drain Hose through the
small hole in the rear of the fibre-
glass toilet shell. Feed the hose
through until the liquid drain valve
connection side is resting just on
the inside of the shell near the
front edge.
The hose exiting through the hole
in the shell should lead through
the hole previously cut into the
bathroom wall and out towards
the absorption trench.
Wall
Shell
Liquid Drain Hose
50mm PVC
Pipe
Wallace
Grommet
Construct the excess liquid drain absorption trench as per the following diagrams.
Also note that the liquid drain hose when installed must always allow the liquid to
continuously run downhill.