23
Version 1.0
Operating manual
SOA-1022
3
INTENDED USE
3.1
Operational limitations
Select an installation place in compliance with operational limitations (operating
temperature and protection degree).
All SC shall be grounded; all cables shall be insulated.
3.2
Usage preparations
3.2.1
Safety features
While preparing the SC for operation, check them visually and make sure there
is no mechanical damage.
Connect the SC to power supply considering input power requirements.
Before connection, transfer all automatic circuit breakers of the SC and external
power sources to “Off” position; the System shall be grounded.
While using the System the staff shall follow “The technical rules for operation
of electric installation” and “Safety rules for operation of electric installation” while
testing electrical circuits and insulation resistance.
3.2.2
Visual check procedure
Before switching the SC on, the installer shall:
– observe visually integrity and initial position of automatic circuit breakers of
CSAHS;
– clean the SC from dust and dirt by clean soft cloth, if necessary;
– check fail-safe cable connections to the SC and their proper grounding.
3.3
Intended use
To switch the System on, an installer shall follow the steps below:
‒
connect main and standby power supply to the Product;
‒
connect AHU to CSAHS (if there is one AHU);
‒
connect AHU to КР, then connect КР to CSAHS (if there are 2 to 20 AHUs);
‒
transfer automatic circuit breakers of main and standby power supply
(CSAHS) to top position;
‒
wait for repeater software to download;
‒
make sure that the System is operating correctly.