Step 1: Assemble weatherproofing
gland on cable as shown
Step 2: Strip the outer insulation
Step 3: Arrange conductors as shown in
Figure 18 and cut to length
Step 4: Insert conductors and crimp
Figure 17: Completed ODU connector
Both ends of the ODU cable are terminated in the same way. The above procedure should be
repeated for the 30/60 Mbps PIDU end of the cable when the cable routing process is complete.
Note: The 30/60 Mbps PIDU end of the cable does not employ a cable gland.