ODU and must be grounded to the ODU. For mast installations, the Surge Arrestor Unit should
be mounted at the same height as the ODU.
The lower Surge Arrestor Unit should be mounted at the building entry point and must be
grounded.
The termination of the CAT-5 Cable into the Surge Arrestor Unit is illustrated in Table 11, Table
12 and Figure 77. The screen from the cable must be terminated into the ground terminal within
the unit to ensure the continuity of the screen. Earth Sleeving should be used to cover the shield
ground connection to prevent internal shorting within the unit.
Terminal
Id
tifi
ti
Conductor RJ45
Pin
CON3 Pin 1
Orange/White
1
CON3 Pin 2
Orange
2
CON3 Pin 3
Green/White
3
CON3 Pin 6
Green
6
CON1 Pin 4
Blue
4
CON1 Pin 5
Blue/White
5
CON1 Pin 7
Brown/White
7
CON1 Pin 8
Brown
8
Summary of Contents for MOTOwi4 Canopy 30
Page 1: ...Canopy 30 60 Mbps Backhaul User Guide BH30 60 UG en Issue 3 1 July 2006 ...
Page 73: ...Issue 3 1 July 2006 Page 73 of 162 Figure 41 Fixed Frequency Operation Page 2 ...
Page 74: ...Issue 3 1 July 2006 Page 74 of 162 Figure 42 Installation Wizard Confirm Configuration Normal ...
Page 104: ...Issue 3 1 July 2006 Page 104 of 162 Figure 69 System Reboot ...
Page 124: ...Issue 3 1 July 2006 Page 124 of 162 Figure 75 Upper Grounding Configuration ...