04. INSTALLATION

04. INSTALLATION

SPRING ADJUSTMENT

TOP COVER REMOVAL

01•

 Open the door using the key 

supplied to unlock it and then pull it to 

the outside.

03•

 The hooks that secure the top cover 

are also rotated and release the cover.

02•

 Rotate the rod (image above) to 

unlock the cover. There are two rods, 

one on each side of the barrier.

04•

 Pull the cover up to remove it.

ADJUSTMENT•

 To adjust the springs, you 

must use a wrench to fasten or release 

the springs nuts. If you rotate them 

clockwise you are giving tension to 

the springs causing the boom to rise 

up, and rotating counterclockwise you 

are removing tension from the springs 

causing the boom to descend.

01•

 Unlock the barrier (please follow steps on page 03.B)

02•

 Put the boom like on phase 1 as shown on the above image. Let it go and it must 

maintain on that position, or rising very slowly. If the boom starts to descend or rise 

adjust the springs untill you can make the boom become stabilized.

03•

 Put the boom like on phase 2, phase 3, phase 4 and phase 5 and repeat the same 

process of point 2 for each phase. With the adjustment of the springs, you must 

achieve a stage where you can let go the boom in each position you desire and it must 

stay stabilized. The springs must be calibrated to sustain the total wheight of the 

boom without the help of the motor.

04•

 When the springs are tuned, lock the barrier following the steps on page 03.B.

When assembling the top cover on the barrier, you must do the exact same steps but 

in reverse order.

Boom Length

Number of 

Springs

Spring’s Length and 

Steel Diameter

<3600mm

1

440mm (1 spring de Ø5mm)

3600 - 5000mm

1

440mm (1 spring de Ø6mm)

5000 - 6000mm

2

440mm (1x Ø5mm + 1x Ø6mm)

PHASE 5

PHASE 4

PHASE 3

PHASE 2

PHASE 1

Summary of Contents for mbm6

Page 1: ...v4 0 REV 01 2019 EN INSTALLER AND USER S MANUAL BARRIER MBM6...

Page 2: ...el of mechanical assemblies in doors and gates and control board programmation He should also be able to perform electrical connections in compliance with all applicable regulations The installer shou...

Page 3: ...9 04 M16 bolts with bushings 10 04 boom fastening screws 11 02 boom support fastening screws 12 01 RGB LED board 13 01 cover for boom 14 01 installer and user s manual TECHNICAL SPECIFICATIONS 03 OPER...

Page 4: ...ier s warning light During pausing time while openned warning light emits BLUE light During closing course warning light emits RED light 01 Open the door using the key supplied with the barrier Rotate...

Page 5: ...the barrier 02 Solder the bolts with bushings on the foundation while the cement is still fresh It is also necessary to respect the dimensions on the side image when soldering the bolts so that the ba...

Page 6: ...om is fixed use the cover to hide these fastening parts After assembling the boom you must define the length of it so that you can fix the boom support as visible on the image above When the boom s le...

Page 7: ...on phase 1 as shown on the above image Let it go and it must maintain on that position or rising very slowly If the boom starts to descend or rise adjust the springs untill you can make the boom becom...

Page 8: ...fixed to the boom s rotation shaft that when openning or closing will activate the micro switches also installed This will cause the control board to stop the barrier when the micro switches are activ...

Reviews: