03. INSTALLATION
PRE-INSTALLATION
PRE-INSTALLATION
Before starting the installation check the wall alignment.
If it is not flat, you must create shims, so that the tightening points of the awning to the wall
are perfectly aligned and level. You should also make sure that the metal bushings / screws
are tightened onto a sturdy surface so there is no risk of loosening and dropping the awning.
You should never open the safe without installation being complete as it may endanger your
physical integrity.
These points are very important because the safety and stability of the awning reside
mainly in its fixing!
For correct functioning of the awning, it is mandatory to place the supports in the identified areas. Always
place 1 support on each side of the armrest and divide the rest evenly. Never change the placement of
the armrests!
The COFRE brackets are not in the correct installation location when shipped from the
factory, proceed as shown in the following images.
Awning between
4200mm and 5500mm
Awning between
5501mm and 6500mm
Awning between
6501mm and 7000mm
4
supports
5
supports
6
supports
Measure the place where the Awning will be applied, always keeping in mind the leveling of the wall
supports for the Awning attachment.
INSTALLATION OF COFRE UP TO 5500MM (2 ARMS) -
the
4
supports (B) must be placed 20mm away from
the awning arms.
INSTALLATION OF COFRE FROM 5501MM TO 6500MM (2 ARMS) -
the
5
supports (B) must be fully abutted
with a 20mm distance from the awning arms, and also a support centered with the holder .
WALL WITHOUT CONDITIONS FOR INSTALLATION
WALL WITH THE SHIMS NEEDED FOR INSTALLATION
INSTALLING OF COFRE FROM 6501MM TO 7000MM (3 ARMS) -
the
6
supports (B) must be fully abutted and
20mm away from the awning arm. The awning arm should be centered with the holder .