ZX Fire Alarm Control Panels
Page 36
Document No. 996-174-000-1, Revision: 01
Installation Manual
5 Maintenance
5.1 Maintenance
Schedule
The following Maintenance routine as recommended in EN54-14 should be adopted.
5.1.1 Daily Attention
The user should check the following:
1. The panel should indicate normal operation and if not the fault should be recorded in a logbook and
reported to the servicing organization.
2. Any faults previously reported have received attention.
5.1.2 Monthly
Attention
The user should check the following:
1. Any stand-by generators should be started and fuel levels checked.
2. At least one call point or detector (from different zones each month) should be operated to test the
fire panel and any connected alarm/ warning devices.
3. Where permissible, any link to the fire brigade or remote manned centre should be operated.
Any faults should be recorded in the log book and corrective action taken as soon as possible.
5.1.3 Quarterly Attention
The service organization should arrange to test the following:
1. Check entries in the logbook & inspect the panel’s log, taking appropriate remedial action where
necessary.
2. Examine all battery connections.
3. Check the alarm, fault and ancillary functions of the control and indicating equipment.
4. Visually inspect the control and indicating equipment for any moisture ingress or other
deterioration.
5. Enquire if any structural alterations have been made which could affect the operation of call points,
detectors or sounders, if so carry out a visual inspection.
Any defects should be recorded in the logbook and corrective action taken as soon as possible.
5.1.4 Yearly
Attention
The service organization should arrange to test the following:
1. Carry out the test and inspection routines recommended daily, monthly & quarterly.
2. ‘Walk Test’ the system and check that each detector operates in accordance with the
manufacturer’s recommendations.
3. Visually inspect all cable fittings and ensure equipment is secure, undamaged and adequately
protected.
4. Examine and test all batteries NB: Note the expected operating life shown in Section E.
Any defects should be recorded in the logbook and corrective action taken as soon as possible.