Page 14 of 22
Rev B
–
Dec 2009
INSTALLATION INSTRUCTION
1. Position hoist to installation position on two bearers.
2. Open wooden create and layout contents.
3. Remove packing straps and blocks.
4. Position and bolt down through the 6 fastening holes. The recommended fastener is a 20mm expansion sleeve type
fastener, min length of 82mm. Where shims are required to correct for out of level floors, the shims must support the full
length of the roller track.
Safety
Toggle
Fastening holes Fastening holes
5. Locate the control unit in an appropriate position away from the hoist. A qualified electrician must wire the control unit.
Refer to Electrical diagram Page 15. Fill tank through breather vent with the supplied Hydraulic oil.
6. Dry filtered compressed air at 6 to 7 bar line pressure is required to operate the safety mechanism. The control unit is
supplied via an inline particulate filter which requires a ¼”BSP threaded fitting from
a min 6mm ID supply line.
7. Attach the hydraulic hose from the control unit to the hoist. The connection is under the Left (passenger side) wheel
run up ramp. Insure all hydraulic fittings are tight and not leaking, refer to page 15 Betabite Hydraulics Assembly
Instructions. Optional connection can be made under Right wheel run up ramp by relocating the pipework end plug
fitting.
8. Connect electrical limit switch wires and pneumatic airline to connection points at front left hand of hoist. Secure with
The Hydraulic line and U shape cover. Optional connections can be made under Right wheel run up ramp.
9. The hydraulic hose, electrical wires and pneumatic airline must be protected from accidental damage. Use 6mm (1/4”)
wall plugs to secure supplied covers to the ground. Extra covers are available, please contact your local supplier.
10. Raise the hoist and inspect hoist for correct operation and that the safety toggles are locking.
11. Install the run up/run off ramps and centre cover onto the hoist. Swap pickup extension so handles are on the
outside of the scissor lift.
12. NOTE: For efficient operation of your hoist please adhere to the maintenance schedule
Summary of Contents for SL02
Page 4: ...Page 4 of 22 Rev B Dec 2009 Model SL02 Complies fully with the Australian Standard 1418 9 1996...
Page 13: ...Page 13 of 22 Rev B Dec 2009...
Page 16: ...Page 16 of 22 Rev B Dec 2009 ELECTRICAL DIAGRAM WIRING TO THIS UNIT TO COMPLY WITH AS3000...
Page 17: ...Page 17 of 22 Rev B Dec 2009 ELECTRONIC DIAGRAM...
Page 18: ...Page 18 of 22 Rev B Dec 2009 HYDRAULIC DIAGRAM...
Page 21: ...Page 21 of 22 Rev B Dec 2009...