Do the signal cables meet regulations? (Type, diameter)
Checkpoint
1
No.
2
Is the signal cable wired at least 5 cm away from the power supply cable?
3
Are multiple transmission or signal cables wired to the same power cable
duct?
4
Are multiple signal cables wired with multi core cables?
5
Are the signal cables securely connected to the terminals?
6
Are the signal cables connected to the specified terminal blocks?
Operation monitor, operation monitor with delay function 1
: TM4
9
,
0
Malfunction monitor
: TM3
7
,
8
Bypass operation monitor, operation monitor with delay function 2 : TM3
6
,
7
7
Are the output capacities of the operation monitor, malfunction monitor, and
bypass operation monitor within the ratings?
Action
Use specified cables.
Wire the signal cable at least 5 cm
away from the power supply cable.
Wire the transmission cables away
from the signal cables.
Using suitable cables, wire the sig-
nal cables so that they are separat-
ed from one another.
Connect them securely.
Connect them to the specified termi-
nal blocks.
Use within the ratings.
Signal cables to external devices (Table 1-1-4)
Check the following checkpoints when outputting the operation monitor, air supply fan operation monitor, mal-
function monitor, bypass operation monitor, and operation monitor with delay function.
8
When using the operation monitor, is the setting of the output signal cor-
rect?
<When using PZ-60DR-E>
Check the operation monitor setting
from the function selection.
(Refer to page 41)
<When not using PZ-60DR-E>
Check the setting of the operation
monitor (SW5-2) on the Lossnay cir-
cuit board. (Refer to page 38)
9
When using the operation monitor with delay function, is the setting of the
output signal correct?
Check the settings of the TM4
9
,
0
output setting (SW2-8), and the
TM3
6
,
7
output setting (SW5-6)
on the Lossnay circuit board.
(Refer to page 38)
10
When PZ-60DR-E is not used, are the function selection switches (SW2,
SW5) on the Lossnay circuit board set correctly?
Set the switches correctly to corre-
spond with the application.
(Refer to page 38 and 39)
11
When PZ-60DR-E is used, is the function selection set correctly?
Set it correctly to correspond with
the application.
(Refer to page 40 to 42)
Output
Maximum rating
Minimum rating
Operation monitor
Operation monitor with delay function 1
240 V AC 2 A
24 V DC 2 A
220 V AC 100 mA
5 V DC 100 mA
Malfunction monitor
240 V AC 1 A
24 V DC 1 A
220 V AC 100 mA
5 V DC 100 mA
Bypass operation monitor
Operation monitor with delay function 2
240 V AC 1 A
24 V DC 1 A
220 V AC 100 mA
5 V DC 100 mA
—48—
Summary of Contents for LGH-100RX5-E
Page 4: ...4 2 Specifications...
Page 5: ...5...
Page 6: ...6...
Page 7: ...7...
Page 8: ...8...
Page 9: ...Unit mm LGH 15RX5 E 3 Outside dimensions 9...
Page 10: ...Unit mm LGH 25RX5 E 10...
Page 11: ...Unit mm LGH 35RX5 E 11...
Page 12: ...12 Unit mm LGH 50RX5 E...
Page 13: ...Unit mm LGH 65RX5 E 13...
Page 14: ...14 Unit mm LGH 80RX5 E...
Page 15: ...Unit mm LGH 100RX5 E 15...
Page 16: ...16 Unit mm LGH 150RX5 E...
Page 17: ...Unit mm LGH 200RX5 E 17...