I
Read Before Servicing ]
- 10 -
HWE09070
GB
[8] Vacuum Drying (Evacuation)
1. Vacuum pump with a reverse-flow check valve (Photo1)
To prevent the vacuum pump oil from flowing into the refrigerant circuit during power OFF or power failure, use a vacuum
pump with a reverse-flow check valve.
A reverse-flow check valve may also be added to the vacuum pump currently in use.
2. Standard of vacuum degree (Photo 2)
Use a vacuum pump that attains 0.5Torr(65Pa) or lower degree of vacuum after 5 minutes of operation, and connect it directly
to the vacuum gauge. Use a pump well-maintained with an appropriate lubricant. A poorly maintained vacuum pump may not
be able to attain the desired degree of vacuum.
3. Required precision of vacuum gauge
Use a vacuum gauge that registers a vacuum degree of 5Torr(650Pa) and measures at intervals of 1Torr(130Pa). (A recom-
mended vacuum gauge is shown in Photo2.)
Do not use a commonly used gauge manifold because it cannot register a vacuum degree of 5Torr(650Pa).
4. Evacuation
time
After the degree of vacuum has reached 5Torr(650Pa), evacuate for an additional 1 hour. (A thorough vacuum drying re-
moves moisture in the pipes.)
Verify that the vacuum degree has not risen by more than 1Torr(130Pa) 1hour after evacuation. A rise by less than
1Torr(130Pa) is acceptable.
If the vacuum is lost by more than 1Torr(130Pa), conduct evacuation, following the instructions in section 6. Special vacuum
drying.
5. Procedures for stopping vacuum pump
To prevent the reverse flow of vacuum pump oil, open the relief valve on the vacuum pump side, or draw in air by loosening
the charge hose, and then stop the operation.
The same procedures should be followed when stopping a vacuum pump with a reverse-flow check valve.
6. Special vacuum drying
When 5Torr(650Pa) or lower degree of vacuum cannot be attained after 3 hours of evacuation, it is likely that water has pen-
etrated the system or that there is a leak.
If water infiltrates the system, break the vacuum with nitrogen. Pressurize the system with nitrogen gas to
0.5kgf/cm
2
G(0.05MPa) and evacuate again. Repeat this cycle of pressurizing and evacuation either until the degree of vac-
uum below 5Torr(650Pa) is attained or until the pressure stops rising.
Only use nitrogen gas for vacuum breaking. (The use of oxygen may result in an explosion.)
(Photo1) 15010H
(Photo2) 14010
Recommended vacuum gauge:
ROBINAIR 14010 Thermistor Vacuum Gauge
Summary of Contents for CMB-PW202V-J
Page 1: ...Service Handbook AIR CONDITIONERS MODEL CMB PW202V J ...
Page 9: ...HWE09070 GB ...
Page 11: ... 2 ...
Page 25: ... 16 ...
Page 28: ... II Restrictions 19 HWE09070 GB ...
Page 31: ... 22 II Restrictions GB HWE09070 ...
Page 37: ... 28 ...
Page 40: ... III WCB Components 31 HWE09070 GB 3 WCB Circuit Board SW1 SW2 SW5 SW6 SW4 ...
Page 41: ... 32 III WCB Components GB HWE09070 ...
Page 42: ... 33 HWE09070 GB IV Electrical Wiring Diagram 1 Electrical Wiring Diagram of the WCB 35 ...
Page 43: ... 34 ...
Page 45: ... 36 IV Electrical Wiring Diagram GB HWE09070 ...
Page 47: ... 38 ...
Page 51: ... 42 ...
Page 61: ... 52 VI Control GB HWE09070 ...
Page 63: ... 54 ...
Page 73: ... 64 ...
Page 109: ... 100 ...