background image

AUTOTRANS

LINEATOR™ 

 

ATL-M001-A2 

 

 

 3.0 Maintenance 

 

 

 

 

WARNING  

 

Internal maintenance must be 
performed with a transformer de-
energized, isolated and with the 
terminals grounded. 

 

 
 

 

3.1 Periodic Inspection and Maintenance 

 

The

 

AUTOTRANS

L

INEATOR

 

has no moving or 

active parts and therefore requires only minimal 
periodic maintenance when installed in a clean 
and well ventilated environment. This should 
include:

 

 

3.1.1  Visual inspection for evidence of loose 

connections, dirt, moisture, rusting, 
corrosion, and deterioration of the 
insulation, varnish or paint. 

 

Observations should be made for signs 
of overheating and overvoltage creeping. 
Corrective measures should be taken as 
necessary

3.1.2  For early detection of any developing 

hotspots, an infrared scan can be 
performed  

while 

the 

AUTOTRANS

L

INEATOR

 is operating under 

its heaviest load condition. 

3.1.3 

Measuring the current in each of the 3 

phases of the capacitor circuit can be a 
quick and easy method of determining 
the condition of the capacitors. The 
capacitors can be assumed to be in good 
operating condition when all 3 phases 
carry approximately the same amount of 
load current. Measurements should be 
taken at the input to the capacitor fuse 
block and can be done at any loading 
condition. If the phase currents are found 
to be substantially different, the unit 
should be taken offline and serviced by a 
qualified technician. This test should be 
conducted annually or whenever the unit 
seems to be operating in an abnormal 
manner.

 

 

 
3.2 Cleaning 

 

Excessive accumulations of dirt on the transformer 
windings or insulators and capacitor terminals 
should be removed to permit free circulation of air 
and to guard against the possibility of insulation 
breakdown. Particular attention should be given to 
cleaning the top and bottom ends of the winding 
assemblies and to cleaning out ventilating ducts. 
Windings should be lightly cleaned by the use of a 
vacuum cleaner. If necessary a blower or 
compressed air may be used but pressure should 
not exceed 25 psi. Lead supports, tap changers 
and terminal boards, bushings, and other major 
insulating surfaces should be brushed or wiped 
with a dry cloth. The use of liquid cleaners is not 
recommended due to deteriorating effects on most 
insulating materials.  
 

 

3.3 Drying of Core and Coil Assembly

 

 

 

 

 

 

CAUTION  

 

Constant attention during the 
drying process is recommended.  
 
 
 

 

When it is necessary to dry a

 

AUTOTRANS

L

INEATOR

 transformer 

before 

installation or after an extended shutdown under 
relatively high humidity conditions, internal and/or 
external heating methods can be used. (See 
ANSI/IEEE C57.94-1982 for a description of these 
methods).

 

 

It is important that most of the heated air pass 
through the winding ducts and not around the 
sides. Good ventilation is essential in order that 
condensation not take place in the reactor itself or 
inside the case. A sufficient quantity of air should 
be used to assure approximately equal inlet and 
outlet temperatures.  
 

Air temperature should not exceed 70°C. 

Summary of Contents for AUTOTRANSLINEATOR

Page 1: ...MIRUS International Inc INSTALLATION OPERATION AND MAINTENANCE GUIDE AUTOTRANSLINEATOR AUTOTRANSFORMER AND UNIVERSAL HARMONIC FILTER ATL M001 A2...

Page 2: ...d maintenance of the AutoTransLineatorTM and its auxiliary equipment WARNING OPENING ENCLOSURES EXPOSES HAZARDOUS VOLTAGES ALWAYS REFER SERVICE TO QUALIFIED PERSONNEL ONLY WARNING As standards specifi...

Page 3: ...TION OPERATION AND MAINTENANCE GUIDE ATL M001 A2 3 Feb 2010 MIRUS International Inc 31 Sun Pac Blvd Brampton Ontario Canada L6S 5P6 1 888 TO MIRUS 1 888 866 4787 Tel 905 494 1120 Fax 905 494 1140 E Ma...

Page 4: ...warranty period and obtain a written return material authorization an RMA from MIRUS The Customer must return the defective unit to MIRUS freight prepaid within sixty 60 days of receipt of the RMA an...

Page 5: ...Page 1 0 Installation 1 1 1 Location 1 1 2 Inspection 1 1 3 Handling 1 1 4 Grounding 1 2 0 Storage 1 3 0 Maintenance 2 3 1 Periodic Inspection and Maintenance 2 3 2 Cleaning 2 3 3 Drying of Core and...

Page 6: ...AUTOTRANSLINEATOR vi ATL M001 A2...

Page 7: ...spection should be conducted with emphasis on loose or broken connections damaged or displaced parts cracked insulators dirt or foreign material or evidence of moisture 1 3 Handling The AUTOTRANSLINEA...

Page 8: ...uld be conducted annually or whenever the unit seems to be operating in an abnormal manner 3 2 Cleaning Excessive accumulations of dirt on the transformer windings or insulators and capacitor terminal...

Page 9: ...e reactor will prevent condensation If a shutdown exceeding 24 hours occurs during a period of high humidity that could cause condensation within the transformer precautions should be taken Small stri...

Page 10: ...AUTOTRANSLINEATOR 4 ATL M001 A2 NOTES...

Page 11: ...Operation Maintenance Manual ATL M001 A2 5...

Page 12: ...US International Inc 31 Sun Pac Blvd Brampton Ontario Canada L6S 5P6 1 888 TO MIRUS 1 888 866 4787 Tel 905 494 1120 Fax 905 494 1140 E Mail mirus mirusinternational com Website www mirusinternational...