NOTICE
Welding or lightning strike current flowing through the cell can damage it.
All electrical welding on the weighing system must be finished before mounting the load
cells.
When installing the load cell, immediately bypass the load cell with a flexible copper
strap (included in the load cell equipment).
During any additional electrical welding work near the load cell:
-
Disconnect the load cell cables.
-
Bypass the load cell using the flexible copper strap.
-
Make sure that the grounding clamp of the welding set is fitted as closely as possible
to the welding joint.
5.3.2
Installing the mounting kit and inserting the load cell
Note:
Screw mounting of the upper and lower plates is described below.
The operations must be performed at all supporting points (e.g., vessel) of the weighing
object.
The load cell must always be mounted with the load disc downwards.
Requirements:
-
All threaded holes for the lower plate are available in the foundation/substructure
(see Chapter
).
-
All threaded holes for the upper plate are available in the vessel lug/vessel foot (see
Chapter
).
5 Installation
Maxi FLEX and Maxi FLEXLOCK mounting kits PR 6012/02, ../32, ../42
Minebea Intec
EN-21