2 Prepare boiler
continued
Draft hood & spill switch
Draft hood installation
1. Secure draft hood to flue collector hood with sheet metal
screws. See Figure 20, items 1 and 9, on page 26. Use boiler
cement to provide gas tight seal.
Failure to maintain gas‑tight seal can cause flue gas
spillage and carbon monoxide emissions, resulting
in severe personal injury or death.
Do not alter boiler draft hood or place any obstruction
or non-approved vent damper in breeching or vent
system. CSA certification will become void. Flue gas
spillage and carbon monoxide emissions will occur
causing severe personal injury or death.
Screw 10–32 x 3/8”
Screw #6 x ½”
Boiler cement
Access panel
Rollout TFE
63904-GSA
GSA-300
P
Burner
Pilot burner
Pilot
Legend:
P
Figure 10
Access panel
Figure 9
Burner drawer installation
Figure 8
Burner and pilot burner location
Figure 7
Burner drawer assembly
Figure 6
Front base panel
Jacket installation
(up to GSA‑300)
1. Remove the proper knockout discs from panels as shown
in Table 4, page 7.
2. Follow Jacket Instructions in jacket carton.
Spill switch installation
1. Fasten spill switch to draft hood as shown in Figure 20, item
20, page 26.
2. See wiring diagram in GSA Spark Ignition Control Supple-
ment to connect wires.