NOTE:
Material damage occurred due to
unprofessional operating!
Start-up without sufficient quantity of water
destroys device
Turn on the boiler and use it only if there
is sufficient quantity of water
NOTE:
Material damage due to incorrect
handling!
Instruct client/user how to handle device
6.
Commissioning
When complete below described works fill in the
Commissioning log (chapter 6.3).
6.1
Before commissioning
Boiler must work with minimum pressure of 0.7 bars
Before turn on, test if the following elements and joints are
connecter correctly and work correctly:
Watertight of heating installation
All pipes connected into ducts
All electric connectors
6.3
Start-up log
6.2
First turn on
Prior to turn on check if heating installation is filled with
water and air-vent
Turn on main switcher (below device)
Heating system and device parameters will appear on
display
Device is adjusted by default on min temperature of 10°C
and power of 0 kW
Only the pressure value in installation on display will be the
one which you adjusted during filling the installation with
water
Commissioning
1.
Boiler type
2.
Serial number
3.
Set thermostat regulation
4.
Fill and air-vent heating installation and check sealing of
all connectors
5.
Establish working pressure
Check expansion dish pressure
_______________ bar
_______________ bar
6.
Test safety devices
7.
Set electric connection according to local regulations
8.
Test function
9.
Users informed, technical documentation submitted
10.
Notes
11.
Certificate of professional turn on device
Service seal / Signature / Date
Table
5:
Start-up log