MNBE-8D2x2 Instructions (continued)
5 |
P a g e 1 0 - 2 4 5 - 1 R E V : A
Step 5:
Install bottom as shown. Use ¼-20 nuts
supplied. (Door not shown)
Step 3:
Apply silicone sealant (not included)
around the entire top edge.
Step 3 continued:
Apply extra silicone sealant around holes
and corners.
Step 4:
Install top to the sides as shown.
Use ¼-20 nuts supplied. (Door not shown)
Step 2:
Stand battery box upright. Line up the hinges on
the door with the hinge pins on the battery box
and lower the door onto the hinge pins.
Important!
The door must go on before the top cover.
Step 2 Continued:
Door Installed on Hinges