7.7 Balance refrigerant of the 2-way, 3-way valves
Procedure:
1. Confirm that both the 2-way and 3-way valves are set to the open position.
2. Connect the charge set to the 3-way valve’s service port.
Leave the valve on the charge set closed.
Connect the charge hose with the push pin to the service port.
3. Open the valves (Low side) on the charge set and discharge the refrigerant until the gauge indicates 0.05 to
0.1Mpa.
If there is no air in the refrigeration cycle [the pressure when the air conditioner is not running is higher than
0.1Mpa, discharge the refrigerant until the gauge indicates 0.05 to 0.1 Mpa. If this is the case, it will not be
necessary to apply an evacuation.
Discharge the refrigeration gradually; if it is discharged too suddenly, the refrigeration oil sill be discharged.
Summary of Contents for MSV1-09HRDN1-QC2
Page 9: ...6 3 Dimension 3 1 Indoor Unit MSV1 09HRDN1 QC2 A 795 165 270 MSV1 12HRDN1 QC2 A 285 845 165...
Page 10: ...7 3 2 Outdoor Unit MOC 09HDN1 QC2 MOC 12HDN1 QC2...
Page 12: ...9 5 Refrigerant cycle diagram...
Page 13: ...10 6 Wiring diagram 6 1 Indoor Unit MSV1 09HRDN1 QC2 A MSV1 12HRDN1 QC2 A...
Page 14: ...11 6 2 Outdoor Unit MOC 09HDN1 QC2 MOC 12HDN1 QC2...
Page 36: ...33 LED1 LED4 LED5 LED6...