7) Using 2 preliminary mounting holes and installer's choice 

    of hardware, attach the SRSR base to millwork 

    (See FIGURE B). Remove the “Locking Trim Panel” and 

    carefully test the sliding operation of the system. 

    To close, use lockout lever. Should interference in the 

    millwork occur it may be necessary to fine tune the

    mounting location (simply loosen the preliminary 

    mounting points and adjust as necessary).

8) Using the preliminary mounting screws for support, extend 

     the sliding carriage to the outer most position.  Finish 

     attaching the base to the host enclosure using 

     customer-supplied hardware. (See FIGURE C on pg. 4 for the 

     correct number of mounting points required per application) 

     VERY IMPORTANT - Use all the mounting points designated 

     when affixing the base to the host enclosure.

9) Slide rack into closed position and attach 

     the locking trim panel.

NOTE:  When fully extended, a lockout feature secures the

rack in open position.

Removal of rack from base:  To remove, extend rack

and remove the four wing nuts on bottom of frame. 

Pick up rack lifting from the sides using handles

provided.  To reattach, extend slides and lift rack 

onto rotating base aligning studs on rack with

holes on base. (Rack should click in securely) 

Install four wing nuts from the underside of 

base and tighten.

SRSR RACK REMOVAL

INSTRUCTIONS

WING NUT

Preliminary

mounting

holes

FRONT

FIGURE B

BOTTOM

PAN

LOCKING 

TRIM PANEL

SQUARING

PANEL

REAR 

RACKRAIL

FRONT

RACKRAIL

HANDLE

ROTATING

TAB

LOCKOUT

LEVER

Summary of Contents for SRSR Series

Page 1: ...R Series Rotating Sliding Rail System Please read these instructions thoroughly before installing assembling this product PRODUCT FEATURES Provides easy access to rear equipment connections Ideal for...

Page 2: ...25 rackspace SRSR s only using flange nuts provided HINT Rack removes from base allowing off site equipment integration see pg 3 for instructions 4 Install squaring panels approximately 1 3 of the wa...

Page 3: ...ect number of mounting points required per application VERY IMPORTANT Use all the mounting points designated when affixing the base to the host enclosure 9 Slide rack into closed position and attach t...

Page 4: ...when cabling is complete PROPER METHOD OF FASTENING CABLES USING WIRE TIES HINT LEAVE THIS LOOSE FASTEN CABLES APPROXIMATELY 3 FROM END SHOWN EXTENDED AND ROTATED WITH TWO SETS OF WIRES FOR CLARIFICAT...

Page 5: ...RSR 4 SRSR X FIGURE C Preliminary Mounting Holes Preliminary Mounting Holes 12 Additional mounting holes as shown 18 97 482 281 dia 7 15 78 401 2 78 71 1 59 40 0 00 0 from trim 9 59 244 19 19 487 8 0...

Page 6: ...ket and adhere gasket to bottom of rackrail where shown Gently pull gasket up to top of rack while removing backing Align gasket at top of rackrail and adhere Press firmly along length of gasket 3 Con...

Page 7: ...tion or maintenance THIS WARRANTY IS IN LIEU OF ALL OTHER WARRANTIES OF ANY KIND EITHER EXPRESSED OR IMPLIED INCLUDING BUT NOT LIMITED TO IMPLIED WARRANTIES OF MERCHANTABILITY AND FITNESS FOR A PARTIC...

Reviews: