METAL-FACH
Heating Technology
43
Report on the first start-up of the boiler
(Copy of the owner of the central heating boiler )
In order to verify the purchase and recognize the validity of the warranty, a report must be sent within 30 days
from the date of the first start-up. These activities can be performed by:
1.
E-mail - in which the scan or photo of the report will be posted.
2.
Letter - in which a copy of the report for METAL-FACH Jacek Kucharewicz will be sent, the company's
address is at the end of the Technical and Movement Document.
Boiler
Fulfills
It does not
Comment
The conditions included in the Operation and Maintenance Manual
in the chapter "Requirements for the boiler room and boiler
installation" are complied with.
The conditions specified in the Operation and Maintenance Manual
in the chapter "Connecting the boiler to the chimney" section are
complied with.
Central heating system.
Fulfills
It does not
Comment
The conditions specified in the Operation and Maintenance Manual
in the chapter "Connecting the boiler with the heating system" are
complied with.
The conditions specified in the Operation and Maintenance Manual
in the chapter "Requirements for the expansion vessel " are
complied with.
There is no other source of heating. If it exists, and how does it affect
the operation of the boiler?
System frost protection.
Connecting elements with electrical installation
Fulfills
It does not
Comment
The conditions included in the Operation and Maintenance Manual
in the chapter "Connecting the boiler to the electrical system" are
complied with.
Fixture test
Fulfills
It does not
Comment
The sensors are placed in the right place.
The sensor readings are consistent with the actual state.
The direction of rotation of the fan is correct.
Fan flap is opened by blowing force.
The direction of rotation of the screw is correct.
Boiler commissioning
Fulfills
It does not
Comment
The tightness of the hydraulic connection of the boiler to the system
is maintained.
system test (if installed).
Checking the connection of the fuel feeder with the boiler.
Backfilling the fuel tank with fuel.
Summary of Contents for SEMAX OPTI 16
Page 2: ......
Page 12: ...METAL FACH Heating Technology 10 Boiler dimensions User Installer Boiler SEMAX OPTI...
Page 32: ...METAL FACH Heating Technology 30...
Page 38: ...METAL FACH Heating Technology 36...
Page 40: ...METAL FACH Heating Technology 38...
Page 42: ...METAL FACH Heating Technology 40...
Page 49: ...METAL FACH Heating Technology 47...
Page 50: ...METAL FACH Heating Technology 48...
Page 51: ......