Please retain product label and instructions for future reference

HANDLE

WITH CARE

1

2

3

4

Felt 

tacks 

Step 17

Parts needed - No.23

Cut the felt into seven strips & lay 

onto the roof in the order shown in 

the illustration.

*Ensure there is approximately 

50mm of overhanging felt each 

side.

Once the felt is laid out fix to the 

roof using felt tacks at 100mm

intervals.

*Felt size: 4530mm

360x Felt Tacks

1.

2.

3.

4.

5.

6.

7.

Roof

Closure Trim

Internal

23

*Measure and cut the

closure trims to

fit the internal space.

23

23

Roof

Closure Trim

Internal

21

*Measure and cut the

closure trims to

fit the internal space.

21

21

Pre drill 

hole

30mm 

screw

*

trim to fit

Step 15

Parts needed - No. 21 QTY 6 

   

 

Inside the building place the closure 

trim (No. 21) against the boarding 

and align with the roof as shown in 

the illustration.

Once in position fix each trim 

into place by pre drilling a pilot hole 

and using 6x30mm screws per trim, 

equally spacing them along the face 

of the board.

36x30mm Screws

30mm 

screw

Pre drill 

hole

*

Cut to fit

Step 16

Parts needed - No. 21 QTY 6 

Once the floor has been laid arrange the

closure trim (No. 21) around the outside 

edge of floor (internally), measure and cut 

down accordingly to best match the 

internal space.

Secure each trim section into place using 

6x30mm spaced equally along the board 

as shown in the illustration.

*Do NOT fix the closure trim to the floor

boards.

36x30mm Screws

 

Summary of Contents for 0628LOG114-V4

Page 1: ...sprayed with water during extended periods of warm sunshine and sheltered as much as possible during rain or snow BUILDING A BASE When thinking about where the building and base are going to be constr...

Page 2: ...x120x4000mm QTY 19 LB28 A 4000 Log Board 28x120x3396mm QTY 2 LB28 AE 3396 11 Log Board WA 28x120x3896mm QTY 2 LB28 AE 3896 12 Log Board WA 28x120x4396mm QTY 2 LB28 AE 4396 13 Bearer 44x44x2804mm QTY 2...

Page 3: ...ered pattern Before securing ensure that the boards are fitted properly in their respective tongues and grooves P 3 Please retain product label and instructions for future reference Felt Tacks x600 70...

Page 4: ...method arrange the remaining framing No 14 as shown in the illustration Ensure there is an equal amount of space between each frame Secure each of the frames in place using 2x70mm screws for each side...

Page 5: ...No 9 QTY 6 Lay the next 6 boards No s 5 6 8 9 onto the assembly to create your second level Ensure that the boards are level and flush with each other as you lay each one Doors can be hung once the b...

Page 6: ...st two boards No s 9 22 onto the front of the assembly Once in position place log board No 12 onto the plain sides fixing into position by screwing through the notches as shown in the illustration Ens...

Page 7: ...Once in position fix to each purlin using 3x40mm screws Due to natural occurences of wood shrinkage expansion You maybe required to use the provided spacers and place a space of 2mm to ensure every ro...

Page 8: ...l Continue adding the floor boards internally making sure to interlock each individual board Do NOT secure the boards until the last board has been measured and cut Measure the gap between the bottom...

Page 9: ...al space 21 21 Pre drill hole 30mm screw trim to fit Step 15 Parts needed No 21 QTY 6 Inside the building place the closure trim No 21 against the boarding and align with the roof as shown in the illu...

Page 10: ...ole 40mm screw Step 19 Parts needed No 20 QTY 8 Arrange the storm braces No 20 around the building internally Place 2x storm braces per side fixing into place using 2x 70mm bolts per brace making sure...

Reviews: