Step 16

Screw through the side panel exter-

nally in line with the 2 x 1 framing 

using 1 x 70mm screw in either side 

to secure the framing in place. 

Screw through the front panel 

externally with 4 x 70mm screws 

equally spaced a part along the door 

frame to secure the 2 x 1 framing to 

the panel.

*Please ensure you pre-drill prior to 

screwing into the panel to eliminate 

the chances of the timber splitting.

       Drill 3 x 6mm holes into the  

2 x 1 framing in line with your 

barrell bolts. These will act as 

the catch for the barrell bolts at 

the top of your door.

* Ensure the holes are drilled in 

to the 2 x 1 framing attached in 

step 15 as oppose to the door 

frame.

A

70mm 

screw

Pre drill 

hole

24

AFTER

Step 15

Place the Door support bar (No. 24) 

to the inside of the door panel as 

displayed on the  pictures. 

This framing will meet at each side 

panel as show in image 2. 

The 44mm side of the framing should 

sit against the inside of the door 

panel, matching the width of the 

door frame timber.

*Ensure that the framing is attached 

in a straight line matching the line of 

the top of the door frame. 

*Please be aware this piece of fram-

ing may need to be adjusted to 

length by customer in regards of 

building tolerances. This piece of 

framing should fit tightly between 

the two side panels.

Hand Saw

BEFORE

Summary of Contents for 03VER0808-V2

Page 1: ...ended periods of rain swelling of the wood panels may occur Warping of the wood may also occur during excessive dry spells due to an interior moisture loss Unfortunately these processes cannot be avoi...

Page 2: ...h 2411mm Width 2484mm Height 2569mm Base Dimensions Length 2350mm Width 2360mm Please retain product label and instructions for future reference Before assembly please make sure you have a suitable ba...

Page 3: ...framing of the door panel using 3x butt hinges per door Fix to the door using 3x25mm screws 3x30mm screws to the framing per hinge ensure the doors open freely folding back into the building unrestri...

Page 4: ...the floor bearers in an alternating pattern Once fixed together turn the floor back the right way up 8x50mm Screws Pre drill hole 50mm screw 2 4 Step 5 Fix the corners with 50mm screws as shown in th...

Page 5: ...nterlock Secure in place using 4x50mm screws per gable top screwing in an alternating pattern 8x50mm Screws Pre drill hole 50mm screw 11 Pre drill hole 25mm screw 12 7 7 Step 9 Attach 2x eaves frames...

Page 6: ...f as shown in the illustration Ensure there is approximately 50mm overhang of felt around all sides of the building Fix into place using 110x felt tacks at 100mm intervals 110x Felt Tacks Felt tacks 1...

Page 7: ...bolts These will act as the catch for the barrell bolts at the top of your door Ensure the holes are drilled in to the 2 x 1 framing attached in step 15 as oppose to the door frame A 70mm screw Pre dr...

Page 8: ...indow cover that sealant is used to keep the building weather tight Step 18 Attach a strip to the hinged side of the middle opening doors These strips allow you to adjust the doors allowing for moistu...