background image

P 5

Please retain product label and instructions for future reference

             

5

22

Step 8

Attach the “L” brackets to each

end of the ridge bar with 

2x25mm screws per bracket.

*Ensure the brackets are flush

with the ends of the ridge bar.

Align the ridge bar between

the gables and secure to the

central uprights with 2x25mm

screws per bracket as shown in

the illustration.

8x25mm Screws

Step 7

Place the gable tops onto the window

panels, ensuring the boards interlock.

Secure in place using 4x50mm screws 

per gable top, screwing in an alternating

pattern.

8x50mm Screws

Pre drill 

hole

50mm 

screw

11

Pre drill 

hole

25mm 

screw

12

7

7

Step 9

Attach 2x eaves frames to

the long side of each roof

sheet, ensuring the frames

are flush to the edges, 

securing in place with 

3x30mm screws per frame.

Place each roof sheet onto

the building and fix into

place using 12x40mm

screws per roof.

12x30mm Screws

24x40mm Screws

Pre drill 

hole

30mm 

screw

40mm 

screw

Step 10

 

Secure the building

 

to the floor using

 

36x50mm screws.

 

*Ensure to screw

 

through the framing

 

into the floor bearers.

36x50mm Screws

Pre drill 

hole

50mm 

screw

5

Summary of Contents for 03VER0808-V2

Page 1: ...ended periods of rain swelling of the wood panels may occur Warping of the wood may also occur during excessive dry spells due to an interior moisture loss Unfortunately these processes cannot be avoi...

Page 2: ...h 2411mm Width 2484mm Height 2569mm Base Dimensions Length 2350mm Width 2360mm Please retain product label and instructions for future reference Before assembly please make sure you have a suitable ba...

Page 3: ...framing of the door panel using 3x butt hinges per door Fix to the door using 3x25mm screws 3x30mm screws to the framing per hinge ensure the doors open freely folding back into the building unrestri...

Page 4: ...the floor bearers in an alternating pattern Once fixed together turn the floor back the right way up 8x50mm Screws Pre drill hole 50mm screw 2 4 Step 5 Fix the corners with 50mm screws as shown in th...

Page 5: ...nterlock Secure in place using 4x50mm screws per gable top screwing in an alternating pattern 8x50mm Screws Pre drill hole 50mm screw 11 Pre drill hole 25mm screw 12 7 7 Step 9 Attach 2x eaves frames...

Page 6: ...f as shown in the illustration Ensure there is approximately 50mm overhang of felt around all sides of the building Fix into place using 110x felt tacks at 100mm intervals 110x Felt Tacks Felt tacks 1...

Page 7: ...bolts These will act as the catch for the barrell bolts at the top of your door Ensure the holes are drilled in to the 2 x 1 framing attached in step 15 as oppose to the door frame A 70mm screw Pre dr...

Page 8: ...indow cover that sealant is used to keep the building weather tight Step 18 Attach a strip to the hinged side of the middle opening doors These strips allow you to adjust the doors allowing for moistu...

Reviews: