Step
1
-Installing the AC branch circuit junction box
A
、
Check and make sure the AC voltage is within the voltage range indicated on the label.
B
、
Mount the Meikai adapter plate at a suitable location on the PV racking system (typically at the
end of a branch of modules).
C
、
Connect the open wire end of the AC interconnect cable into the junction box using an
appropriate gland or strain relief fitting.
D
、
Work out the total current basis on the number of micro-inverters in each branch, use an
appropriate cable and connect the AC branch circuit junction box to the point of utility
interconnection.