SEC-K 

Pressure Sender & Valve connection

 

Incorrect 

Ensure that the valve is correctly installed with regard to the direction of the flow of gas and that the Sender Unit is fitted the 
correct way round. (Note: there is no flow “through” the pressure sender unit, it is purely reading the pressures either side of the 
valve. 

Correct 

Pressur

Solenoid 

Never mount the valve such that the Solenoid or Sender Unit are below the horizontal. 

Inlet Side/Upstream 

Outlet Side/Downstream 

    Direction of flow 

    Gas Solenoid and Sender Unit Mounting 

Pressure sender unit 

Summary of Contents for SEC-K V4

Page 1: ...e call 07894 684080 or 07843 355163 It is a statutory requirement that this safety system is installed and commissioned to the satisfaction of the manufacturer A commissioning certificate must be issu...

Page 2: ...uttons A and B for engineer functions LED indications Power On green A blind button for displaying gas pressures on the LCD screen Gas Electric red when active to warn of live service Fans running lig...

Page 3: ...PTA Over pressure check isolates gas valve if pressure exceeds 70 mbar REV SEN Reverse sender unit if installed incorrectly 17 Fill prove time for gas pressure proving see page 5 18 Timer adjustment f...

Page 4: ...as detectors 1 8 press A B together to view 9 16 Fire Test Mode Press button B three times When connected to a fire alarm panel using the fire alarm terminal no 13 the system will isolate the gas duri...

Page 5: ...1 Option Headers 18 19 21 20 Fan comm To enable the commissioning of the gas portion of the system before the ventilation interlock is completed you may temporarily disable the interlocking by pressin...

Page 6: ...e the gas detectors own instructions for more guidance SEC K Detector Information VE supply Comm s From either the main panel or an extender Detectors are wired in parallel and can be connected to one...

Page 7: ...een 1m and 3m from the potential source Care should be taken so they are not located close to the edge of a canopy or in direct flow of the supply or extract ventilation For additional information or...

Page 8: ...ltiple connect in parallel Live feed through the Medem CM2M K2 channel current Monitor fans Fan speed controls Fan live Supply Fire Alarm Requires a volt free NC contact Where using 3 phase fans inter...

Page 9: ...sent within the panel IMPORTANT If wired this way a warning notice must be attached to the panel to indicate that there are two separate mains feeds Contactor coil Live feed through switched relay To...

Page 10: ...s fitted the correct way round Note there is no flow through the pressure sender unit it is purely reading the pressures either side of the valve Correct Pressur e Solenoid Never mount the valve such...

Page 11: ...Solenoid coil of the valve should never be mounted below the horizontal Pressure sender unit should never be mounted upside down to protect from water ingress Approx 400mm length INLET PORT OUTLET PO...

Page 12: ...d be wired in series with the EM stop buttons To EM Stop connections in the panel Indicator bar shows when pressed Normal EM Stop Activated Multiple Stop Buttons Single Stop Buttons Resetting indicato...

Page 13: ...er Medem UK will exchange faulty valves for return to the manufacturer 5 Where a Medem UK engineer or another company appointed by Medem UK commission and installed system then that system will carry...

Page 14: ...CD display that all the detectors have been recognised by the panel A recognised detector will appear as CO Carbon Monoxide CM combustible CH Carbon Dioxide OX Oxygen depletion and TP Temperature Coun...

Page 15: ...sure test If at any point the fans stop running opening the S1 or E1 contact the system will isolate the gas and report fans not running Check that the fans are not only switched on but actually runni...

Reviews: