7
Lift Roof Frame Assemblies and position
Lift both roof frame assemblies onto the top of the unit as shown so that
the outside edges run parallel to both horizontals. Make sure that the
roof panel groove is on the upper side and that the top ridge extrusions
are at the center of unit as shown in detail C. The front and back of the
roof assemblies should be flush with front of horizontals.
8
0.66in
17mm
Ridge
Top Ridge
Roof panel Groove
Right
Toprail
Left
Toprail
Flush
Temporary secure roof frame assemblies
to Right and Left Toprails.
Secure the outside edges of the roof frame assemblies to the Left Toprail
and Right Toprail at three of the holes with 3, Taptite ¼-20 x 1.0” screws
wax coated per side. Do not fully secure screws to allow roof frames
assemblies to pivot on these screw.
Note:
do not fully secure the screws at this time.