Fuse: 10 amp 115v.
3
.
INITIAL SETTING UP
1.
Remove the bolts holding the machine to the pallet.
2.
Castors are already fitted to the machine, lift from the pallet on to an even surface.
3.
Remove packing from stapling section and from under fold stop beneath the conveyor.
4.
Lower output conveyor, allowing the slotted ends on the support bars (part no. 6.06) to locate on
the protruding bolts provided. These bolts are located at the base of the machine.
5.
Fit the conveyor wheels.
Figure 2 - Conveyor setup.
6.
Insert the conveyor end stop (part no. 6.11) at the far end of the conveyor, making sure it does not
infringe the belt. It is held in position by a flat magnet.
7.
Position the machine near to a suitable socket outlet and ensure outlet is not covered and is easily
accessible.