9.0 MAINTENANCE AND INSPECTION SCHEDULE
It is recommended that maintenance and inspection be done on a scheduled basis, Maintenance
requirements will naturally vary widely for each installation and specific operating conditions. It is
suggested that a complete inspection be performed with necessary maintenance at the end of the
first month, the first three months, and the first six months. These inspections will be indicative of
how often future maintenance will be necessary.
Every Month
A.
Inspect air filters. Clean or replace as required. Replace if cartridge is broken. The time
interval for inspection should be shortened if experience indicates unusual dust loading.
B.
Check system for air leaks or flow obstructions and correct as required.
Every 3 Months
A.
Check heater amperage (see Specification Sheet.)
B.
Check Motor amperage (see Specification Sheet.)
C.
Check all electrical connections to make sure that they have not become loose, especially
those connections at contactors, motor starters, and heater elements.
Once Every Year
Check Solenoid valve operation and operation of valve.
Every 2 Years or as needed
Remove top cover of dryer and replace desiccant. Use high temperature silicon caulking to reseal