Page 39
3.9.8. Continuation of Installation - Trim Switch Control Model
1. Unpack the battery pack and connect to
the battery connection on the cable.
2. Fit the connectors on the cable to the
drive motor ensuring correct polarity. The
cable connectors must be matched to
the appropriately sized spade connector.
Position the battery pack inside the heat
shield (see
Figure 67
).
3. Test the operation of the drive motor
using the trim switches (
2.1.4 - Lighting
Procedure (Optimum Control and
Trim Switch Control)
on page
7
).
4. Proceed to
Section 3.9.10
to
commission the appliance.
4xAA
BATTERIES
Figure 69
3.9.9. Continuation of Installation – Total Control
1. Unpack the box containing the Receiver
and the Hand Set.
2. Fit four AA (1.5V) batteries into the
receiver unit and the PP3 (9V) battery
into the transmitter (hand set).
3. Feed the cables from the valve through
the heat shield and connect to the
receiver as shown in
Figure 70
, keeping
the cables clear of the underside of the
tray. Do not force the valve cable when
inserting into the receiver – it only fits
one way.
4. Position the receiver under the heat
shield as shown in
Figure 67.
5. Test the operation of the drive motor
using the hand set as per Users
Instructions (
Section 2.1.5- Lighting
Procedure (Total Control)
on page
8
).
6. Proceed to
Section 3.9.10
to
commission the appliance
HT
Lead
SW
)
(yellow
TC
( )
red
Valve
Cable
Figure 70