5.0
OPERATING INSTRUCTIONS
5.1
START UP
The following start up procedure should be employed whenever starting the system
after a total shutdown.
1)
Switch on Battery Breaker CB3. This will cause the display to come on and go
through the start-up sequence, briefly display the MAGELLAN logo and show
the top page after a delay of a few seconds.
2)
Switch on Mains Power input circuit breaker (Refer to the schematic drawing).
3)
The charger should now start to deliver some charging current to the battery. If
the batteries are fully charged the voltage will quickly approach the Float level
and the charger current will get reduced.
4)
Switch on the Load Circuit Breaker (Refer to schematic drawing).
5)
The system should now be delivering the load current and charging the
batteries and all alarms would be reset.
5.2
VOLTAGE AND CURRENT DISPLAY
The following parameters are displayed on the front panel LCD:
Screen 1 Charger voltage, Charger Current, Operating Mode and Fault.