background image

 

To install the stainless steel SHAFT RETAINERS, use thumb and forefinger to hold the retainer over the end 
of the PUSH TUBE ( 3/8" x 3" tube, supplied in the kit), internal fingers on retainer dished into tube. HOLD 
THE ELEMENT FIRMLY TO PREVENT IT FROM SLIDING OFF CENTER and press the retainer onto the 
element end and continue until retainer butts on insulator button. Locking pliers, 

lightly

 clamped up against 

opposite button insulator will help maintain center reference (if you push the first retainer too far, remove 
element from boom, push retainer completely off the element, and start over). Install another retainer to the 
opposite side of the element.  Continue installing retainers until all elements are secured. 

 

6.Mount ASSEMBLY to the

 HORIZONTAL

 DRIVEN ELEMENT BLOCK / ROD 

TOP

 of the boom using a single 

8-32 X 1-1/4" screw. Orient the block with the two balun connectors facing to rear. 

 

7.  Install the 8-32 x 1/4” set screws (internal Allen head - tool supplied) into the SHORTING BARS. Slide the 

bars onto the 1/8" Driven Element Block Rods and the 3/16" driven element rod. 

Position the Shorting Bars 

at 1/8" from the tips of the 3/16" rods. 

Align the bars with each other and tighten the set screws. 

 

ASSEMBLING THE VERTICAL ELEMENTS 
 

Note: The vertical element set is shifted forward on the boom by 1/4 wavelength. This increases isolation 
between element planes, improving circularity and ease of phasing / matching the two element sets. 

8.  Repeat steps #2 through #5 for the Vertical elements, using the Dimension Sheet as your guide to lengths 

and spacing. 

 
 

INSTALLATION OF THE 

VERTICAL

 DRIVEN ELEMENT BLOCK DETERMINES THE CIRCULARITYOF 

THIS ANTENNA. THE ORIENTATION OF THE BLOCK FOR RHC - RIGHT HAND CIRCULARITY, IS 
SHOWN ON THE DIMENSION SHEET AND DRAWING AND DESCRIBED BELOW: 

  

9.  Viewed from the rear of the boom (rearmost Reflector HORIZONTAL), the VERTICAL  Driven Element Block 

mounts to the RIGHT hand side of the boom with the two Balun connectors oriented to the REAR. Secure 
with 8-32 x 1-1/4” screw. Install the Shorting Bars as in step #7.  

 
10. Before installing the Baluns and Matching / Phasing Harness. Attach Baluns and Phasing lines to the Driven 

Element Blocks and Junction Block as shown on the Dwg. Tighten the connectors 

gently

 using a 

7/16" 

end wrench. A lot of torque is unnecessary. Depending on model and polarity, the Vertical balun may loop 
around another element. This is normal. Form balun coax until it is close to the boom and secure with a 
nylon cable tie. Also secure the other balun and the matching / phasing harness coax with cable ties. Ties 
should be snug but not crushing or kinking the coax. 

 
 
 
 
 

436CP30 ASSEMBLY MANUAL 

Reviews: