Installation
Hydraulic installations
14
© Lutz-Jesco GmbH 2015
BA-24721-02-V01
Chlorine gas changeover unit C 7523
Operating instructions
7.3 Hydraulic installations
PVC-U pipes or PE hoses are used as conduits. If the line is to supply
multiple consumers, the line should be calculated for the total of the
consumption volume.
The following nominal widths are recommended for the vacuum line
(pressure loss max. 25 bar, calculated at 0.9 bar (a) with 4x90° angles):
Mass flow of
chlorine
Length of the vacuum line between the vacuum regulator and the dosing device
5 m
10 m
20 m
30 m
50 m
100 m
1 kg/hr
DN 8
DN 8
DN 8
DN 8
DN 8
DN 12
2 kg/hr
DN 8
DN 8
DN 8
DN 12
DN 12
DN 12
4 kg/hr
DN 8
DN 12
DN 12
DN 12
DN 12
DN 15
10 kg/hr
DN 12
DN 12
DN 15
DN 15
DN 20
DN 20
15 kg/hr
DN 12
DN 15
DN 20
DN 20
DN 20
DN 25
25 kg/hr
DN15
DN 20
DN 20
DN 25
DN 25
DN 32
40 kg/hr
DN 20
DN 25
DN 25
DN 25
DN 32
DN 32
60 kg/hr
DN 25
DN 25
DN 32
DN 32
DN 32
DN 40
80 kg/hr
DN 32
DN 32
DN 32
DN 32
DN 40
DN 50
Table 8: Max. capacity
Where necessary, a large distance can be installed in a large nominal
width and a connection in the nominal width of the device can be selected
for shorter sections shortly before and after the device.
Fig. 6:
M
M
L
A
L
1
L
B
L
C
L
2
L
D
Long vacuum line
Position
Meaning
a
Vacuum regulator
b
Vacuum changeover unit
c
Dosing device
L
A
-L
D
Lines connected to the device
each with c. 0.5m in the connection nominal width
L
1
,L
2
Large distances in a larger nominal width
The sum L
1
+L
2
may not exceed the length as specified in table 8
Table 9: Long vacuum line
1
2
3