B
ATTERIES
A. Assure
that
All
switches are turned off (including battery switches and switch inside
refrigerator).
B.
Check to see if batteries are charged and install into battery boxes. Connect battery cables.
C.
Install protective positive battery boot over the positive battery terminal.
Check Trim Tab Operation
A.
Check operation of trim tab switches.
B.
Press the Stbd/Bow up switch. The port trim tab should go up.
C.
Press the Stbd/Bow down switch. The port trim tab should go down.
D.
Press the Port/Bow up switch. The starboard trim tab should go up.
E.
Press the Port/Bow down switch. The starboard trim tab should go down.
Launching Boat
Launch the boat, leaving it in the sling until the following initial checkout is complete.
Initial Checkout:
A.
Check the shaft logs (2) where applicable, rudders, shaft strut mounting bolts (12) where
applicable, garboard drain plugs, and through hull exhaust for leaks.
B.
Check the following through hull fittings for leaks: Refer to owner manual for the location of
through hulls.
Cooling water inlet (2) where applicable.
Exhaust outlet (2) where applicable
Generator water inlet (1) where applicable
Air Conditioning inlet (1) where applicable
Toilet inlet (1)
Macerator outlet (1)
C.
Open through hull valves and check for leaks.
D.
Check drain plugs on mufflers.
Total Task Time:
N/A
31-Open
Rigging Manual
Page:
9 of 15
Note: There should be No spark when the battery cable touches the battery
Terminal.