Lucent Technologies Lineage
®
2000 100A Ferroresonant Rectifier J85503A-1
Issue 6 October 1998
Installation 5 - 1
5
Installation
Introduction
This section provides information to consider before installing
the J85503A-1 rectifier in a Lineage
®
2000 Battery Plant. The
section also describes the input and output wiring required and
the recommended procedure for installing the rectifier from
uncrating through startup. Lucent Technologies offers
“turn-key” engineering and installation services for the products
described in this product manual. Consult your Lucent
Technologies representative for details.
Safety
Please read Section 4, Safety, thoroughly before installing the
J85503A-1 rectifier, and carefully read and follow the
admonishments as they are presented throughout this
documentation.
Preparing for
Installation
Location of the J85503A-1 rectifier and associated equipment
must conform to the specific plans of each Lineage
®
2000 plant
installation. Physical, thermal, and electrical specifications are
given in Section 2. These specifications must be considered in
the plans for any installation that includes this rectifier.
Handling
Equipment
Each J85503A-1 rectifier weighs at least 300 pounds. Therefore,
the customer must make prior arrangements for appropriate
material handling facilities and equipment to unload, uncrate,
and set up the rectifier. Proper handling is necessary to assure
personnel safety and protect the equipment. Each rectifier is
shipped in a tri-walled corrugated cardboard container secured
to a wooden shipping skid. The container should be moved by a
forklift.