Lucent Lineage
®
2000 ECS Battery Plant H569-408
Issue 2 July 1996
Installation 3 - 7
2. Check and set the low-voltage disconnect/reconnect, if
provided, at the desired voltage level. See Figure 3-3 for
the location of the disconnect voltage select jumpers,
J505.1 and J505.2 on LVD/Fuse Board.
a. To provide a disconnect voltage of 42.5 +/- 0.5 volts,
plug the jumpers across pins 1 and 2 of their respective
connectors.
b. To provide a disconnect voltage of 40.5 +/- 0.5 volts,
plug the jumpers across pins 2 and 3 of their respective
connectors.
3. Refer to the ECS controller manual for acceptance testing
procedures for the LVD/Fuse circuit pack and the
associated LVD/R option.
Step E: AC Wiring, Rectifier Installation and Test
Refer to the installation and start-up procedure in the Rectifier
manual for the following steps.
•
Wire AC
•
Set up
•
Plug in
•
Test
Before proceeding, verify that all rectifier output circuit breakers
are in the OFF position.
Note
It is recommended that ac be wired during the initial installation
for all rectifier positions that may be used in the future. If ac is
prewired in this way, growth in rectifier capacity is as simple as
plugging in an additional rectifier.