Lucent Lineage
®
2000 ECS Battery Plant H569-408
Issue 2 July 1996
Installation 3 - 3
3. All dc leads should be separated wherever possible from ac
leads to minimize electrical noise transmitted to the load.
4. Pair the battery potential lead with the associated return
lead of a given circuit for as much of the run as possible.
5. All control leads and other small gauge wiring should be
separated from the ac and dc power leads to prevent
physical damage. (Routing of control leads within the
controller is described in the Controller manual.)
6. All bolts making electrical connections should be torqued
per the values in Table 3-A; all bolts for mechanical
connections should be torqued per values in Table 3-B.
Sequence of
Tasks
Table 3-C lists the drawings, manuals and other documentation
that are necessary to complete the following sequence of tasks.
Step A: Unpacking, Handling & Frame Installation
1. Before opening the packaging, carefully inspect the
outside, in the presence of shipping personnel, for signs of
damage. If damaged, follow the shipping carrier's
procedure for filing a damage claim.
2. To ensure personnel safety and equipment protection use
appropriate equipment during handling of crates and
uncrated equipment. Use the equipment weights and
dimensions given in Section 2 as a guideline for choosing
material handling tools. Move crated equipment to an area
with adequate space and tools for unpacking and handling.
3. Carefully open the packaging to verify that the contents are
complete and undamaged. If the equipment must be
returned, it should be repacked in the original shipping
crate.
Step B: Battery Stand Assembly
Assemble battery stands as described in the battery manual.
Install the batteries onto their stands.
Warning
Do not connect batteries to the system at this time.