Lucent Lineage
®
2000 ECS Battery Plant H569-408
3 - 2 Installation
Issue 2 July 1996
Installation
Tools And Test
Equipment
The following tools and test equipment are required for battery
plant installation and testing.
•
Equipment to handle shipping containers, remove
framework from shipping containers, and erect framework
into final position. Minimum lifting capacity: 500 lbs
•
Common electrician's hand tools
•
Proper crimping tools and dies for connectors used
•
Common mechanic's hand tools
•
30 mm socket wrench
•
24 mm drill bit to bore holes for floor anchors
•
DMM (Digital Multimeter) with at least 0.05% accuracy
on the dc scale
•
DC dummy load bank rated for 75 amperes minimum at 60
volts dc
•
Power supply, variable from zero to 60 volts dc at 2
amperes. Supply should have both coarse and fine output
controls
•
Six clip leads each capable of carrying 3 amperes
Suggested
Installation
Sequence
General
Information
1. The plant may be wired with ac from the left side or the
right side. Typical routing of ac, dc and control cabling is
shown on the plant assembly drawing, H569-408.
Connection points and wire types are indicated on the plant
wiring diagram, T-82670-30.
2. When running dc cable, care should be taken to ensure that
all non-protected leads are run in a separate cable rack
from protected leads. (Protected, in this sense, refers to
overcurrent protection by a fuse or circuit-breaker.)
Battery leads are usually the only unprotected leads. When
Lucent VR Batteries are used, the battery leads may be
protected. Refer to the Battery Manual for more detail on
this option.