INSTRUCTION MANUAL
STEP 1
First remove the Joiner Ring from one of the FUYL Cells that
will become the bottom FUYL Cell of the stack.
Either the FUYL Cell Joiner Ring or the Pedestal can be fixed to
the floor using the 50mm Dynabolts provided. Once in place fix
the M6 studs in place using a screwdriver. Now locate the bottom
FUYL Cell (now without the Joiner Ring) on top of the Joiner Ring
or Pedestal. The 4 studs should locate up through the holes in the
Bottom of the FUYL Cell. Install the M6 nuts and tighten.
Please refer to the FUYL Cell schematic for more details
(back of the booklet).
STEP 3
Now remove the left side panel for the FUYL Cells to be installed above (as described above) to
gain access to the LHS upper/lower, front and rear fixing holes. The RHS holes are in the Laptop
spaces - front and rear. Turn the next FUYL Cell in the stack upside down and locate the M6 studs in
the joiner ring, then fix the FUYL Cell in place. Locate the third FUYL Cell in the same way.
For additional stability of the FUYL Cell stack, it can be secured to the wall behind it using 75mm
Dynabolts provided, through the two top rear holes in the top FUYL Cell, providing the FUYL Cell
stack is located hard up against the wall, this will stop any possible sideways movement in the FUYL
Cell stack.
STEP 2 - Remove the FUYL Cell side panel
• Open all doors
• Unscrew 5 x Phillips head screws on LHS of the front panel.
• Remove the side panel using this technique – Gently pull the front edge of the side panel out
(sideways) from the front (no more than 40mm). Then carefully slide the panel forward to release
its lugs from the rear.
Dynabolt hole
M6 Stud Holes