Siemens servomotor:

GRA326, GNA326, GGA326.

Motorized fire dampers electical wiring

To connect the dampers to the power supply, proceed as follows:

•  Check that the voltage and electrical frequency are equivalent to 

those of the motor of the servomotor (check the motor's informa-

tion label);

•  Make the connections as shown in the below diagram.

Microswitches position for motorized version

1  Negative (DC) or neutral (AC)

2  Positive (DC) or phase (AC)

3 Phase

4 Neutral

S1  Common closed damper microswitch

S2  Normally closed, closed damper microswitch

S3  Normally opened, closed damper microswitch

S4  Common open damper microswitch

S5  Normally closed, open damper microswitch

S6  Normally opened, open damper microswitch

 

„

Electrical specifications

Manual and compact manual

Manual with magnet

Belimo motorized version

Siemens motorized version

Voltage and power consumption

-

Magnet (WKS25MR/MI):

24/48 V DC (automatic voltage switching 

on S0-25 electric board for 24V magnet)
Power interrruption magnet (MR):

P = 1,6 W

Power input magnet (MI):

P = 3,4 W

Motor 24V AC/DC (WKS25VSB):

Belimo BFL24T

Opening: 2,5 W

In stand-by: 0,8 W

230V AC motor (WKS25DSB):

Belimo BFL230T:

Opening: 3,5 W

In stand-by: 1,1 W

Motor 24V AC/DC (WKS25VSS):

Siemens GRA126

Opening: 3,5 W

In stand-by: 2 W

Motor 230V AC (WKS25VSS)

Siemens GRA326

Opening: 4,5 W

In stand-by: 3,5 W

Microswitches position contacts

Manual control version:

12VDC / 2A

125VAC / 0,1A

Motorized version:

Siemens: AC 24V…230V / 6 (2)A

Belimo: DC 5V…AC 250V / 1mA…3A (0,5A)

Blade closing time

Spring: 1 s

motor: < 30 s

Protection degree

IP42

IP42 MAGNETIC VERSION

IP54 MOTORIZED VERSION

MAINTENANCE AND INSPEC TIONS

Fire dampers and control mechanisms do not require routine main-

tenance.

Extraordinary maintenance (repairs) and periodic inspection opera-

tions are the responsibility of the ventilation system operator.

The implementation of a periodic inspection plan allows to guaran-

tee the efficiency and functionality of the fire dampers for the fire 

safety of the building.

 

„

Periodic inspection and cleaning

Periodic inspection shall be performed in accordance with the re-

quirements of the law or by the building regulations or other local 

regulations.

In the absence of specific regulations (or to their complement), in ac-

cordance with point 8.3 of the EN 1560 standard, it is recommended 

to carry out the following control activities at intervals of no more 

than 6 months:

•  If the damper is connected to a remote control or command sys-

tem (eg BMS or alarm or fire detection), that responds correctly to 

commands by performing at least one opening and closing test 

Summary of Contents for EI 120 S

Page 1: ...l data the equipment and acces sories indicated could be subject to variations Installation booklet RECTANGULAR SERIES WKS25 500 Pa Cert N 1812 CPR 1046 EN 15650 This is a 15 page installation booklet...

Page 2: ...sity 995 kg m Plasterboard sealing ve i o D B x H min 100 x 200 max 800 x 600 B x H min 100 x 200 max 800 x 600 B x H min 100 x 200 max 800 x 600 EI 120 S Installation within vertical light wall gypsu...

Page 3: ...l axis Fixing flaps 1 Bend for walls 100 mm thick or higher 2 Bend for walls 70 mm thick or higher Fire dampers pairing The patented WKS25 rectangular fire dampers can be paired side by side or vertic...

Page 4: ...atically closes the blade when the temperature in the duct exceeds 70 C or 95 C for the fire damper with 95 C thermal fuse It is possible to close the damper by pressing the indicated button Blade ope...

Page 5: ...perature sensor or cut off the power supply Blade opening mode The damper must be opened when the ventilation system if switched off To open the damper with the electric motor driven actuator provide...

Page 6: ...Normally open C Common NF Normally closed Manual with magnet MR MI version the magnet is powered using 24 V DC 48 V DC through S0 25 electric board S0 25 electronic board S2 optional for 24V DC 48V DC...

Page 7: ...4V AC DC WKS25VSS Siemens GRA126 Opening 3 5 W In stand by 2 W Motor 230V AC WKS25VSS Siemens GRA326 Opening 4 5 W In stand by 3 5 W Microswitches position contacts Manual control version 12VDC 2A 125...

Page 8: ...itioning The fire damper can be installed both with the blade axis positioned vertically or horizontally Positioning brackets before fixing 1 Positioning brackets Installation of flexible connectors i...

Page 9: ...L1 L2 200 50 50 250 50 100 300 50 100 350 50 150 400 50 150 450 50 200 500 50 200 550 50 250 600 100 250 H Nominal height of fire damper L1 End cap length mechanism side L2 End cap length mechanism o...

Page 10: ...l floor used for the test and wall floor used for the actual installation The test results obtained on a type of wall floor are valid also for walls floor of the same type but with greater thickness a...

Page 11: ...tach to the steel pro file underneath 1 Plasterboard thickness 12 5 mm 2 Rock wool density up to 100 kg m optional 3 Horizontal U shaped profile 4 Vertical C shaped profile 5 Self drilling screw 3 5 X...

Page 12: ...located on the fire damper casing See section Fixing flaps for further details Position the damper in the opening so that the side of the closing mechanism extends from the wall by 185 mm Be careful n...

Page 13: ...r both in relation to air flow and the side with the higher probability of exposure to fire as indicated in standard EN1366 2 paragraph 6 2 Filling It is not necessary to insert any material but simpl...

Page 14: ...5 mm 2 Self drilling screw 3 5 X 45 mm EI 120 S Installation within vertical light wall gypsum blocks wall The WKS25 fire dampers classified EI 120 S within vertical light walls built with gypsum bloc...

Page 15: ...al wall Installation within vertical light wall Shaft wall WKS25 fire dampers are tested and approved in Fire resistance classification Hole size D1 x D2 mm Damper protrusion from the wall E mm Wall m...

Reviews: