Chapter 2 Single UPS Installation And Commissioning 13
Liebert
®
ITA 10kVA UPS User Manual
UPS
Bracket (2 pcs)
M4 × 10
screw (6 pcs)
Installation
hole 1
Installation
hole 2
Bracket
Figure 2-7 Installing brackets
警告
危 险
Note
It is prohibited to move the UPS through the brackets.
3. Install the guide rails.
The installation procedures of the guide rails are as follows:
1) Take out the guide rails (one left guide rail and one right guide rail), guide rail screws and panel screws from the
package, distinguish the left guide rail and right guide rail according to Figure 2-8, and confirm its retractable function
respectively.
Left guide rail
Installation
hole (6 pcs)
Right guide rail
Figure 2-8 Appearance of guide rail
Distinguish the guide rail screw and the panel screw according to Figure 2-9.
Panel screw
Guide rail screw
Figure 2-9 Guide rail screw and panel screw
2) Adjust the length of the guide rails according to the dimensions of the rack.
3) Align the installation holes of the guide rail with the square holes of the rack, fix the guide rail onto the rack with the
guide rail screws, each left guide rail and right guide rail need four guide rail screws, as shown in Figure 2-10.