Configuring Your Neutral and Ground Connections
20
6.6
Preferred Grounding Configuration, Battery Systems
Open-rack battery systems
, depending on local code requirements and customer preference, are
normally:
1. Floating (ungrounded),
2. Center-tapped and floating or
3. Center tapped and grounded.
Battery cabinet systems
must be connected as floating (ungrounded) systems—
Option 1
above.
Center-tapped or grounded battery systems are not possible with battery cabinet systems.
Whether the battery system is open-rack or cabinet, the metal rack parts or cabinet must be grounded
to the UPS module ground bus.
Figure 10
illustrates how a simple, one-cabinet system would be grounded. For systems with multi-
ple cabinets, the same configuration would apply. However, for simplicity, the installer can connect
all the battery cabinet grounds for a particular module together and run a single ground conductor to
that UPS module ground (in the same conduit as the phase conductors).
Figure 10 Preferred grounding configuration, battery systems
Summary of Contents for SERIES 610
Page 6: ...iv...
Page 45: ...Installation Drawings 39 Figure 20 Battery power pack system 88 797616 03 Rev 08...
Page 46: ...Installation Drawings 40 Figure 21 Battery power pack Size A 88 797616 01 Rev 10...
Page 80: ...Installation Drawings 74...
Page 85: ...Site Planning Data Series 610 100 225kVA Multi Module Systems 79 NOTES...
Page 86: ...Site Planning Data Series 610 100 225kVA Multi Module Systems 80...
Page 87: ......