Electrical Installation

 

Mechanical Installation

 

 

 

 

 

 

 

General Wiring

 

•LG  Electronics  recommends  that  all  wiring  be 
double  insulated  with  a  minimum  rating  of  90°C 
(194°F). 
•All   wiring   should   use   a   flexible   copper   (Cu) 
conductor. 
•The  minimum  size  should  be  determined  by  the 
applicable codes. 
•We recommend a size not smaller than 4mm

2

 

Earth Grounding

 

•The  solar  modules  from  LG  Electronics  meet  the 
conditions of safety class II. Therefore grounding is 
not 

mandatory. 

However 

grounding 

is 

recommended.  Also  equipotential  bonding  must  be 
realized. The national directives must be respected. 
•Specific  information  on  the  solar  module 
dimensions  and  location  of  grounding  holes  is 
provided in ‘Product Specifications’. 
•One  M4  stainless  steel  bolt,  one  nut,  one  spring 
washer,  two  flat  washers,  one  cup  washer,  one 
star  washer  and  12  AWG  Cu  wires  are 
recommended per solar module. 
•There is an earth hole in the center of the module 
frame. Using this hole, an  earth  conductor and  the 
solar  module  frame  may  be  recommended  to 
connected and earthed as the below drawing. 
•  To  prevent  electric  shock  and  fire,  a  protective 
ground  must  be  done  on  the  frames  of  solar 
modules  and  arrays  although  the  solar  modules 
from  LG  meet  the  conditions  of  safety  class 

The national directives must be respected. 

 

 

 

Module frame 

 

Bolt 

 

 

Flat washer 
Star washer 

 

 

Cup washer 

 

Grounding wire 
Flat washer 
Spring washer 

Nut 

Module Mounting

 

• The  LG  Electronics’  (LGE)  Limited  Warranty  for 

solar  modules  is  contingent  upon  modules  being 
mounted  in  accordance  with  the  requirements 
described in this section. 

• The solar modules are in Application Class A and 

have  the  Safety  Class  II.  Therefore  they  can  be 
operated  in  systems  with  120  V  DC  and  higher. 
General access is not restricted. 

 

Site Consideration

 

LGE  solar  modules  should  be mounted  in  a  loca- 
tion that meets the following requirements. 

Operating Temperature

 

• Maximum Operating Temperature: +90°C (194°F) 
• Minimum Operating Temperature: -40°C (-40°F) 

Excluded Operating Environments

 

•  The  solar  modules  from  LG  Electronics  can  be 

operated  in  a  location  where  they  could  come  in 
contact  with  salt  water  or  ammonia,  if  they  have 
been  tested  successfully  for  these  operating 
conditions. Please see related certificates. Please 
get  a  release  from  LG  Electronics  for  increased 
conditions. 

Design Strength

 

• Snow loads(Front side, 60Cell) : 6000 Pascal 
• Wind loads(Rear side, 60Cell) : 5400 Pascal 
• Snow loads(Front side, 72Cell) : 5400 Pascal 
• Wind loads(Rear side, 72Cell) : 4300 Pascal 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

60Cell

 

 

① 

: 200mm

 

② 

: 300mm

 

 

 

72Cell

 

 

 

① 

: 300mm

 

※ 

This mounting method is by using frame bolt holes.

 

※ 

The mounting rails must run perpendicularly to the 

module 

long side.

 

• Use corrosion resistant material mounting rails 

and hardware. 

• Use appropriate bolted connections as per 

manufacturer’s instructions. 

• No electrical parts like cables are located after 

installation between laminate and mounting 
structure. 

Mounting
Rails 

 

6

 

Summary of Contents for LG300N1T-A5

Page 1: ...tallation manual PV Solar MODULE Please read this manual carefully before operating your set and retain it for future reference N TYPE MODEL LGXXXN1T A5 LGXXXN2T A5 P NO MFL69668602 Rev 00 www lg solar com ...

Page 2: ...ation 5 4 Mechanical Installation 6 5 Product Specifications 8 6 Disclaimer of Liability Disposal 10 7 Transporting and Storage 10 8 Appendix 11 Revisions Table Date Version Description of change Remark 2016 12 20 1 0 1st edition Publish Installation Manual 2017 08 14 2 0 Change M Load Spec ...

Page 3: ...Cable bending radius should be more than 4 times the cable diameter at least Please use proper equipment connector wire and buttress for system configuration of the module It may result in damage or failure of the product Do not perform installation in rainy heavily windy or snowy days It may result in safety accident Do not make holes in the frame or glass of the module It may decrease the streng...

Page 4: ...d in the carton until the time of installation Make sure flammable gases are not generated near the installation site Do not work alone Please work as part of a team of two or more people Wear a safety belt if working high above the ground Contact with electrically active parts of the panels such as terminals can result in burns sparks and lethal shock whether the panel is connected or disconnecte...

Page 5: ...ermined by basis on max system voltage the 125 safety factor and the module Voc which can be checked in Product Specifications in this document Series connection for more voltage Parallel Connection The solar modules may be combined in parallel to produce the desired current output When modules are combined in parallel the total current is equal to the sum of currents from each module The voltage ...

Page 6: ...ounding wire Flat washer Spring washer Nut Module Mounting The LG Electronics LGE Limited Warranty for solar modules is contingent upon modules being mounted in accordance with the requirements described in this section The solar modules are in Application Class A and have the Safety Class II Therefore they can be operated in systems with 120 V DC and higher General access is not restricted Site C...

Page 7: ...thods Torque 8 12Nm When installing modules in heavy snow areas special care should be taken to install the modules in a manner that provides sufficient design strength while meeting local code requirements Mounting by using frame bolts holes Secure the solar module to the structure using the factory mounting holes Four M8 stainless steel bolts four nuts four spring washers and eight flat washers ...

Page 8: ...G335N1T A5 Yes 335 0 3 41 2 10 28 35 1 9 55 19 20 1000 MC4 PV JM601A 1730 1024 40 18 2 LG340N1T A5 Yes 340 0 3 41 3 10 32 35 5 9 59 19 20 1000 MC4 PV JM601A 1730 1024 40 18 2 LG345N1T A5 Yes 345 0 3 41 4 10 36 35 9 9 62 19 20 1000 MC4 PV JM601A 1730 1024 40 18 2 LGXXXN2T A5 LG360N2T A5 Yes 360 0 3 48 6 9 91 38 8 9 29 16 20 1000 MC4 PV JM601A 2064 1024 40 22 0 LG365N2T A5 Yes 365 0 3 48 7 9 95 39 3...

Page 9: ...9 Product Specifications Dimensions of Modules 60Cell Module Unit mm 72Cell Module ...

Page 10: ... should be disposed of separately from the municipal waste stream 2 Old electrical products can contain hazardous substances so correct disposal of your old appliance will help prevent potential negative consequences for the environment and human health Your old appliance may contain reusable parts that could be used to repair other products and other valuable materials that can be recycled to con...

Page 11: ...0Pa Fig 5 Clamping Type Fig 6 Clamping Type C A B B A C A B 4 point installation is allowed in the following cases 1 Slope roof If module is installed parallel to the rooftop 2 Flat roof If installed with an additional stand such as wind A 200mm B 400mm Front 6000Pa Rear 5400Pa A 120mm 4point Front 1800Pa Rear 1800Pa C 120mm Front 3200Pa Rear 1800Pa A 120mm B 843 100mm 6point Front 6000Pa Rear 540...

Page 12: ...ig 6 Clamping Type C A B B A C A B 4 point installation is allowed in the following cases 1 Slope roof If module is installed parallel to the rooftop 2 Flat roof If installed with an additional stand such as wind A 250mm B 400mm Front 5400Pa Rear 4300Pa A 120mm 4point Front 1600Pa Rear 1600Pa C 120mm Front 3200Pa Rear 1600Pa A 120mm B 1012 100mm 6point Front 5400Pa Rear 4300Pa Note All mechanical ...

Page 13: ...rs are recommended per solar module Clamp system requirements The clamp should not be touched with the module s glass Use corrosion resistant material clamps and hardware If you use a special clamp it needs to test for compatibility by LGE Use appropriate bolted connections as per clamp manufacturer s instructions Follow the clamp manufacturer s recommended applied torque to fasten the clamps Widt...

Page 14: ...n 1 Module height 0 6 1 5m 2 Albedo 0 15 0 85 3 Tilt angle 30º south face latitude 36º 4 Array distance 4 5m Racking Scene 2 lows landscape installation 1 low portrait installation H H H is a minimum height from mounting ground to module LGE recommended a minimum height of 1m ...

Page 15: ...8 Yeoui daero Yeongdeungpo gu Seoul 150 721 Korea Contact solarinfo lge com http www lg solar com This document is subject to change without notice LG LG logo and Life s Good are trademarks of LG Electronics Inc worldwide Trademarks and intellectual properties of LG Electronics Inc are protected by international copyright laws Document II A5 T IEC V1 EN 201612 ...

Reviews: