INSTALLATION OF INDOOR, OUTDOOR UNIT
ENGLISH
Foundation for Installation
• Check the strength and level of the installation ground so that the unit will not cause any
operating vibration or noise after installation.
• Fix the unit securely by means of the foundation bolts. (Prepare 4sets of M12 foundation bolts,
nuts and washers each which are available on the market.)
• It is best to screw in the foundation bolts until their length are 20 mm from the foundation
surface.
* The feature can be changed according to the type of model.
[Unit:mm]
Foundation bolt executing method
200
1012
361
Nut
75
75
200
Spring washer
Frame
Anti-vibration
materials
Four bolt are
required
3 thread ridges
H-Beam
Concrete
base
100
WARNING
• Be sure to remove the Pallet(Wood Support) of
the bottom side of the unit Base Pan before fixing
the bolt. It may cause the unstable state of the
unit settlement, and may cause freezing of the
heat exchanger resulting in abnormal operations.
• Be sure to remove the Pallet(Wood Support) of
the bottom side of the unit before welding. Not
removing Pallet(Wood Support) causes hazard of
fire during welding.
!
Pallet(Wood Support)
- Remove before Installation