Notes:
Cables that connect to the storage tray are longer than the cables that connect to the
compute tray. For optimal cable routing, you should replace the following cables when converting
from a storage tray to a compute tray in the upper-tray position:
• Fan cage cable. Replace part number 01GW929 with part number 01GW928.
• Drive power cable. Replace part number 01GW930 with part number 01GW917.
• Drive Signal cable. Replace part number 01GW931 with part number 01GW918.
Complete the following steps to convert a storage tray to a compute tray:
a. Remove the upper tray from the server if you have not already done so.
http://thinksystem.lenovofiles.com/help/topic/7X12/remove_the_storage_tray.html
b. Disconnect all cables from the storage boards.
http://thinksystem.lenovofiles.com/help/topic/7X12/cable_routing_common.html
thinksystem.lenovofiles.com/help/topic/7X12/cable_routing_for_drives.html
.
c. Remove the storage board assembly.
http://thinksystem.lenovofiles.com/help/topic/7X12/remove_the_storage_board.html
d. Install the system board into the lower bay in the tray.
http://thinksystem.lenovofiles.com/help/topic/7X12/install_the_compute_system_board.html
.
e. Connect cables to the lower system board.
http://thinksystem.lenovofiles.com/help/topic/7X12/cable_routing_common.html
thinksystem.lenovofiles.com/help/topic/7X12/cable_routing_for_drives.html
.
f. Install the system board into the upper bay in the tray.
http://thinksystem.lenovofiles.com/help/topic/7X12/install_the_compute_system_board.html
.
g. Connect cables to the upper system board.
http://thinksystem.lenovofiles.com/help/topic/7X12/cable_routing_common.html
thinksystem.lenovofiles.com/help/topic/7X12/cable_routing_for_drives.html
.
h. Remove the fan fillers in fan bay 8, 10, and 12, and install fans in those bays.
http://thinksystem.lenovofiles.com/help/topic/7X12/install_the_fan.html
Step 10. Install the server back into a rack.
See the
ThinkSystem SR950 Rack Installation Instructions
, which is available here:
http://thinksystem.lenovofiles.com/help/topic/7X12/pdf_files.html
Step 11. Install all the compute tray and I/O tray that were removed.
• For compute tray installation instructions, see
http://thinksystem.lenovofiles.com/help/topic/7X12/
.
• For I/O tray installation instructions, see
http://thinksystem.lenovofiles.com/help/topic/7X12/install_
Step 12. Install the front cover. See “Install the front cover” on page 322.
After installation is complete, reconnect all external cables and power on the server.
252
ThinkSystem SR950 Setup Guide
Summary of Contents for ThinkSystem SR950
Page 1: ...ThinkSystem SR950 Setup Guide Machine Types 7X12 7X11 and 7X13 ...
Page 55: ...Figure 22 Server components Chapter 2 Server components 51 ...
Page 276: ...272 ThinkSystem SR950 Setup Guide ...
Page 282: ...278 ThinkSystem SR950 Setup Guide ...
Page 286: ...282 ThinkSystem SR950 Setup Guide ...
Page 389: ......
Page 390: ......