Launch TLT235
、
TLT240 Economical Two-post User’s Manual
15
8. Tools for Installation and
Adjustment
To ensure proper installation and adjustment, please
prepare the following tools:
:
Tool Model
Leveling instrument
Carpentry type
Chalk line
Min 4.5m
Hammer 1.5kg
Medium crescent wrench
40mm
Open-end wrench set
11mm-23mm
Ratchet socket set
Flat Screw driver
150mm
Rotary hammer drill
20mm
Concrete drill-bit
¢
19mm
9. Unpacking
Open the packing box; remove the packing materials and
inspect the lift for any sign of shipment damage. Check by
packing list to see if the main parts and accessories are
complete.
Keep the packing materials away from the children to avoid
danger; if the packing materials cause the pollution, they
shall be treated properly.
10. Installation
10.1 Important notice
z
The wrong installation will cause the lift damage or
personal injury. The manufacturer will not undertake
any responsibilities for any damage caused due to
incorrect installation and usage of this equipment,
whether directly or indirectly.
z
The correct installation location shall be “horizontal”
floor to ensure the horizontal lifting. The slightly slope
floor can be corrected by proper shimming. Any big
slope will affect the height of the lifting pad when at
the bottom or the horizontal lifting. If the floor is of
questionable slope, consider a visual inspection, or
pour a new horizontal concrete slab if possible. In
short, under the optimum horizontal lifting status, the
level of the lifting relies on the level of the floor where
it is installed. Don’t expect to compensate for the
serious slope.
z
Don’t install the lift on any asphalt surface or any
surface other than concrete. The lift must be installed
on concrete floor conforming to the minimum
requirement showed in this manual. Don’t install the
lift on the concrete with seams or crack and defect.
Please check together with the architect.
z
Without the written approval of the architect, don’t
install the lift on a second floor with basement.
z
Overhead obstruction: The lift installation area can’t
have any overhead obstruction, such as heater,
building support, electrical pipe, etc.
z
Concrete drilling test: The installation personnel can
test the concrete thickness at each site by drilling test.
If several lifts are installed at one place, it is preferred
to make drilling test in each site.
z
Power supply: Get ready the power supply before the
installation. All the electric wiring and connecting
should be performed by a certified electrician.
10.2 Installation Procedure
10.2.1 Selecting installation site
Selecting installation site based on the following conditions:
z
Lift can only be installed on concrete slab, which
must have a minimum thickness of 250mm and
should be aged 7days at least .
z
The concrete slab shall have reinforcement by steel
bar.
z
The concrete slab must be leveled.
z
If the thickness of the whole ground concrete is
greater than 250mm, the lift can be installed directly
z
Check the possible obstruction, e.g. low ceiling, top
pipeline, working area, passage, exit, etc.
z
The front and back of the lift should be reserved with
sufficient space to accommodate all the vehicles (Fig.
8).(evaluating from the center line ,each edge should
be about 4m)
Summary of Contents for TLT235
Page 11: ...Launch TLT235 TLT240 Economical Two post User s Manual 4 Fig 1b Fig 1c...
Page 12: ...Launch TLT235 TLT240 Economical Two post User s Manual 5 Fig 2a Fig 2b...
Page 30: ...Launch TLT235 TLT240 Economical Two post User s Manual 23 Fig 14a...
Page 36: ...Launch TLT235 TLT240 Economical Two post User s Manual 29 Applicable to TLT235SB TLT240SB...
Page 37: ...Launch TLT235 TLT240 Economical Two post User s Manual 30 Applicable to TLT235SB TLT240SB...
Page 38: ...Launch TLT235 TLT240 Economical Two post User s Manual 31 Applicable to TLT235SC TLT240SC...
Page 46: ...Launch TLT235 TLT240 Economical Two post User s Manual 39 1 packing 1 packing Domestic...