background image

 

3

START UP 

 

1.  Place disconnect switch and control circuit 

switch in the OFF position. Fill system with 
water to pre-determined cold fill pressure (one 
pound of pressure is required for every 2.31 
feet of piping system height above the 
pressure gauge). 

 
2.  Purge all air at the highest point in the system 

and vent all points where air is likely to be 
trapped. 

 
3.  Energize circulator pump and verify direction 

of rotation on three phase units. DO NOT 

energize the boiler unless circulator pump is 
operating. 

 
4.  Close boiler control panel door and energize 

the main disconnect switch. 

 
5.  Check all piping connections and valves for 

leaks. 

 
6.  Turn boiler control circuit switch to the ON 

position. If contactor(s) do not close, see 
service section (page 4). 

 
 

MAINTENANCE 

 

A periodic check of all control components will 
ensure proper operation. 
 
1.  Check wiring and terminations for tightness. 
 
2.  Check all controls and safety devises for 

proper operation. 

 
3.  Check pressure relief valve to ensure that it is 

not leaking and that no corrosion exists. 

 
4. 

Check circulator pump and lubricate 
according to manufacturer’s instructions. 

 
At least once a year, boiler elements should be 
checked.  
 
1.  Disconnect all power to boiler. 
 
2.  If a faulty open element is indicated, the 

element may be replaced in the following 
manner: 

 

a.  Isolate boiler from system by closing hand 

valves in supply and return piping. 

 
b.  Drain boiler completely of water. 

 

c.  Remove ALL wiring from the elements, 

tagging both the wires and element 
terminals. 

 

d.  Mark element flange position with respect 

to the vessel flange for proper alignment 
upon reinstallation; remove flange bolts. 

 

e. Remove the element flange from the 

vessel. 

 

f.  Remove element retaining nut using a 

11/16 socket wrench. 

 

g. Remove ferrules (2 compressed rings) 

from the element ends and remove 
element from back side of flange. 

 

h. Insert new element and ferrules and 

tighten element retaining nuts into flange. 

 

i.  Replace flange in boiler vessel using new 

gasket. Align previously made marks on 
flanges and install flange bolts, torqueing 
each bolt to 70 foot pounds (minimum). 

 

j.  Reconnect electrical wiring, making sure 

all wiring is connected to the proper 
element termination. 

 

k.  Refill boiler following procedure listed in 

INSTALLATION section. 

 

l.  Check elements and flanges for leaks. 

 

m.  Replace vessel enclosure cover. 

 

n.  Turn disconnect on. 

 

Summary of Contents for SPACE SAVER

Page 1: ...standby heat source for solar hydronic and water source heat pump systems Vessel ASME Code Section IV H stamped National Board registered rated to 160 psig and 250 degrees Fahrenheit Insulation 4 fiberglass blanket on vessel Elements Incoloy sheathed 75 watts per inch mounted in 150 pound ASA steel flange individually removable Enclosure Ventilated integral control panel constructed of heavy gauge...

Page 2: ...talled on a level non combustible surface 5 Connect the supply and return piping according to applicable codes Pipe relief valve discharge to nearest floor drain or downward away from any potential hazard to other equipment or personnel 6 Boiler feed connection may be tee d into return connection 7 Electrical knockouts are provided for wiring access All wiring must conform to applicable codes and ...

Page 3: ...e according to manufacturer s instructions At least once a year boiler elements should be checked 1 Disconnect all power to boiler 2 If a faulty open element is indicated the element may be replaced in the following manner a Isolate boiler from system by closing hand valves in supply and return piping b Drain boiler completely of water c Remove ALL wiring from the elements tagging both the wires a...

Page 4: ...m damage caused by overheating Automatic Reset High Temperature Cutout s De energizes control circuit in the event of a high temperature condition Control Circuit Lighted Switch De energizes control circuit not main power Operating Controller Maintains water temperature at predetermined setting Pressure Relief Valve Vents pressure to atmosphere in the even of high pressure in excess of relief valv...

Page 5: ...control 2 Water temperature too low Operating control set too low or not operating properly oversized circulator pump or faulty elements fuses contactors wiring 3 Water temperature is too high Operating control is set too high or not operating properly undersized circulator pump or not operating properly 4 Water temperature correct but building is cold Circulator pump not operating properly air bl...

Page 6: ...for which the Purchaser may be liable to other persons or damages to property The remedies set forth in this Warranty are exclusive and the liability of Lattner with respect to any contract or sale shall not exceed the cost of repair or replacement of the boiler or other equipment manufactured by Lattner The above Warranty shall not apply to any boiler or other equipment manufactured by Lattner wh...

Page 7: ...ges in transit and a minimum 15 restocking charge and only if the authorized material is in new and unused condition and returned within one year from original date of shipment The credit will be based on the original invoice price or the current price whichever is lower less the applicable restocking charge SECURITY INTEREST For the purposes of securing payment the Company may issue a lien on the...

Reviews: