background image

Page 2 of 5

DIRECTIONS FOR INSTALLATION

ASSEMBLY :

1.)  Disassemble the Connector assembly as shown in 

Figure 2

.  Loosen clamp guide setscrew and turn clamp guide 

assembly to remove from connector body.  Loosen connector body setscrew and turn connector body to remove from 

acceptor receptacle body.  

2.)  Slide clamp guide assembly, with cable clamp properly assembled, and the grommet washer over the power cable 

being used.  Refer to National Electrical Code Table 400-5 or Canadian Electrical Code Table 12 when selecting the 

conductor size.  

3.)  Determine how many “inner layers” of the onion skin grommet are to 

REMAIN

 

by simply removing the “inner layers” 

until the grommet slips over the power cable.  Remove the “inner layers” as needed from the grommet, one layer at a 

time, by pushing through to solid side and tearing off. See 

Figure 3

.

4.)  Place the onion skin grommet over the power cable with the “SOLID” side facing the clamp guide assembly and slide 

connector body over power cable.  

5.) 

 

WIRING

:

Loosen the terminal screws on the terminal base.  

NOTE:

 

Use 

only

 

copper wire with this device (10, 12 or 14 AWG).

 

Reference 

Figure 4

 

to strip the cable jacket and individual wires.  Recommended conductor connection is crimp fork or 

ring terminals; or loop the wires and attach them to the proper terminal screws: Green lead (Ground, if provided) to screw 

at Ground strap (marked Green); White (Neutral) lead to terminal at White mark (125V. only); Black and/or Red [Line 

lead(s)] to unmarked terminal(s).  See 

Figure 5

.  Hand tighten terminal screws to 10 in.-lbs. of torque.

6.)  Thread connector body onto Acceptor receptacle body and tighten until Acceptor gasket thickness has compressed by 

at least half of its original thickness.  Hand tighten connector body setscrew to 8 in.-lbs. of torque.

7.)  Slide onion skin grommet down power cable into connector body.  Force power cable into connector body to provide a 

minimum 1/8”

 

strain relief in the wire between clamp and insulator.  Slide grommet washer into clamp guide assembly.  

Screw clamp guide onto connector body.  

8.)  Hand tighten the clamp guide set screw to 10 in.-lbs. of torque.

9.)  Hand tighten the cable clamp screws around power cable to 25 in.-lbs. minimum torque, alternating sides as needed 

to prevent binding.

LID ASSEMBLY or replacement

1.)

 

Remove the existing lid assembly by removing the (2) #8-32 screws holding it in place and ensure that the face of the 

Acceptor receptacle is free of obstructions.

2.)  Align the flat surface of the lid assembly with the flat step feature of the receptacle body and install the lid assembly to 

the receptacle, as shown in 

Figure 2

.

3.)  Utilize the existing or the (2) #8-32 screws provided in the kit to secure the lid.

4.)  Hand tighten the screws evenly; making sure that the inside diameter of the lid gasket seal remains circular and 

undistorted.

OPERATIONAL DATA

1.)  Lift receptacle door and insert plug all the way into the receptacle.

2.)  Turn plug to clockwise limit (45°).  This closes internal contacts and completes circuit.

3.)  Release plug.  Plug will move outward to “LOCK” position.  Check by trying to turn plug without pushing inward; plug 

should not turn.

4.)  To remove plug, push plug inward and turn to counter-clockwise limit (45°).  Pull plug straight out.

LarsonElectronics.com • Phone: 1-800-369-6671 • Email: [email protected]

Reviews: