3-12 FINAL ASSEMBLY
3-12.1
Attach a tractor to the implement and
charge the lift system hydraulics as de-
scribed is
Section 4-4
.
3-12.2
Install the 2 x 16 transport lockouts on
both 4-1/2 x 16 master cylinders on the cen-
ter frame.
3-12.3
The fold systems must be purged of air
and filled with oil BEFORE attempting to fold
the implement. Air in the system will allow
the wings to fall uncontrollably and may re-
sult in implement damage. Follow instruc-
tions for charging the hydraulic fold system
(See Section 4-5)
.
3-12.4
Connect lights to the tractor and verify
operation.
3-12.5
Check tires for proper inflation
3-12.6
Level the Wing Coulter Chisel from front
to rear as described in
Section 4-10
.
3-12.7
Inspect the final implement assembly,
and verify that all bolts have been tightened,
cotter pins spread, and that there are no
leaking hydraulic connections.
CAUTION
TIGHTEN ALL 1-3/4" NUTS TO 1,250
FOOT-POUNDS OF TORQUE (SEE FIG-
URE 3-17.
3-12.8
Rotate each coulter gang to verify that
each gang rotates freely. Adjust any scrap-
ers that may have shifted during shipment or
assembly.
3-12.9
Lubricate the Wing Coulter Chisel at all
locations
(See Section 4-17)
.
3-12.10
Touch up with paint any areas that
may have been scratched during moving,
handling, or assembly.
3-12.11
Thoroughly read and understand the
operating section before using the Coulter
Chisel.
3-26
300
POUNDS
PULL
4 FOOT
torque ft lbs
Figure 3-17 Offset Shank Mount Installation